Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
09-MMP-B8, Mine Management & Systems Analysis — May 2019 sitting. 3-hour closed-book exam, answer all 5 questions for a total of 100 marks, Appendix A (discounted cash-flow factor tables) attached.
Reference texts. Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (pit optimization, truck/shovel matching, mine scheduling); Hartman & Mutmansky (eds.), SME Mining Engineering Handbook (mine life-cycle, project economics, haulage systems); Blank & Tarquin, Engineering Economy (DCF/NPV/IRR/payback); Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide) (Critical Path Method).
Check: every page of the examination is headed “09-MMP-B8 Mine Management & Systems Analysis”. The content below solves the paper as printed.
Check: the data used below are as printed in the exam. (1) Table 1's LoM totals reconcile exactly against their own row sums (LoM ore 16,497 kt, contained 485.0 koz, recovered 397.7 koz, waste 86,468 kt). (2) The Mining unit cost in Table 3 is $11.75/t. (3) Question 2(a) asks for the gross and net value of ore per tonne. (4) The rolling resistance for Question 3's haul route is 6%. (5) Question 4's task table includes the task “Expand u/g diesel powered equipment fleet”. (6) Question 5's 2-D block model is a 5-row×8-column grid, the net processed mineral value is $2,800/tonne, and a 1.5% cutoff grade is stated.
Question 4: Project Scheduling and Analysis (20 marks)
Develop/equip new raises for hoisting and ventilation
12
1
3
Develop new u/g exploration drilling gallery
2
1
4
Complete new u/g exploration drilling program
8
3
5
Develop ore body model and mining schedule
2
4
6
Reconfigure mine ventilation system for new zone
4
2
7
Expand u/g diesel powered equipment fleet
4
6
8
Develop upper mining level for new zone
8
7
9
Develop lower mining level for new zone
12
7
10
Develop slot raises for initial stope blocks
2
8, 9
11
Drill open stoping blastholes for initial 2 stopes
1
10, 5
12
First production from stopes in new zone
0 (milestone)
11, 2
Find. (a) a Gantt chart of all 12 tasks; (b) the critical path and shortest project duration by CPM.
Approach. Compute each task's early start/finish by a forward pass (ES = latest EF of its predecessors, EF = ES + duration), read the project duration off the final milestone's EF, then run a backward pass (LF = earliest LS of successors, LS = LF − duration) to find zero-float tasks, which form the critical path.
Fig. 4.1 — Gantt chart of all 12 tasks (bar position = early start, bar length = duration). Red bars carry zero float and form the critical path.
Backward pass (late start/finish) and critical-path identification. Setting $LF_{12}=46$ and working back through each task's successors, the tasks with zero float ($ES=LS$) are $$\boxed{\text{Critical path: } 1\rightarrow2\rightarrow6\rightarrow7\rightarrow9\rightarrow10\rightarrow11\rightarrow12,\qquad 11+12+4+4+12+2+1+0=46\ \text{months}}$$ Tasks 3, 4, 5 and 8 carry positive float (e.g. Task 8's chain 7→8→10 finishes at month 39/41, four months ahead of Task 9's parallel chain that actually drives Task 10's start) and are not on the critical path.
Fig. 4.2 — CPM activity-on-node network with early/late start and finish per task; red boxes and arrows mark the zero-float critical path.