NivaarExam PrepOfficial exam papers ↗

07-Str-A5 · December 2014

Question 2 of 7: Post-tensioned T-beam with cantilever

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. 07-Str-A5 Advanced Structural Design, National Exams December 2014. Three hours, open-book (handbooks and textbooks permitted, no notes). Seven questions of equal value; any five constitute a complete paper, and only the first five presented are marked. All solutions below answer all seven, because the set is a study resource rather than an exam script. All loads shown on the figures are unfactored.

Design data supplied on the paper (SI). Concrete \(f'_c = 30\ \text{MPa}\); structural steel \(F_y = 350\ \text{MPa}\); rebar \(f_y = 400\ \text{MPa}\). Prestressed concrete: \(f_{ci} = 35\ \text{MPa}\) at transfer, \(f'_c = 50\ \text{MPa}\), \(n = 6\), \(f_{ult} = 1750\ \text{MPa}\), \(f_{y} = 1450\ \text{MPa}\), \(f_{initial} = 1200\ \text{MPa}\), losses \(= 240\ \text{MPa}\), hence \(f_{pe} = 960\ \text{MPa}\).

Reference texts.

Check: load classification. The paper prints the loads as unfactored but does not split them between dead and live. Throughout this solution every printed load is treated as a specified live load and factored at 1.5, while member self-weight is treated as dead and factored at 1.25 (NBCC 2020 combination 2, \(1.25D + 1.5L\)). If a different split is stated on exam day, re-run the same arithmetic with the stated factors — the method is unchanged.

Check: Figure 4 geometry. Read from the drawing on page 4, the beam \(AC\) is \(4 + 8 + 4 = 16\ \text{m}\) long with the rigid joint \(C\) at its right-hand end, directly over the column; the 400 kN acts at \(C\), and the 200 kN loads act at 4 m and 12 m from \(A\). Support \(A\) is drawn with the same circle-on-hatching symbol used for the rollers in Figures 1 and 2, so it is taken as a roller (vertical reaction only); base \(E\) is fixed. The frame is therefore indeterminate to the first degree.



Question 2: Post-tensioned T-beam with cantilever (10 + 5 + 2 + 3 = 20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

QuantityValue
Span \(AB\) (pin at \(A\), roller at \(B\))17 m (6 + 5 + 6)
Cantilever \(BC\)3 m
Point loads (specified live)400 kN at 6 m, 400 kN at 11 m, 60 kN at \(C\)
Concrete\(f'_c = 50\ \text{MPa}\); \(f_{ci} = 35\ \text{MPa}\) at transfer
Strand\(f_{pu} = 1750\), \(f_{py} = 1450\), \(f_{pi} = 1200\) MPa; losses 240 MPa
Effective stress after losses\(f_{pe} = 1200 - 240 = 960\ \text{MPa}\)

Find. (a) T-section dimensions, prestressing-strand area and tendon profile such that no tensile stress occurs at any fibre at transfer or in service; (b) the long-term vertical deflection of the cantilever tip \(C\).

Figure 2 - post-tensioned beam ABC and adopted tendon profile400 kN400 kN60 kNABC6 m5 m6 m17 m3 me = 550 mmcentroidharped tendon - straight between the two point loads
Figure 2 — loading on beam ABC and the adopted harped tendon profile shown to scale inside the beam elevation.

Approach. Size a uniform T-section, compute the service moment envelope including self-weight, then impose the two no-tension conditions — bottom fibre in service and top fibre at transfer — as a cable zone \(M_s/P_e - k_b \le e \le k_t + M_{sw}/P_i\). The prestress force is the smallest value for which that zone is non-empty at every section; the profile is then any curve inside the zone. Deflection follows from the unit-load method on the gross section, amplified for creep.

  1. Trial section and properties. Take a flange \(2000 \times 200\ \text{mm}\) over a \(450\ \text{mm}\) web, overall depth \(h = 1600\ \text{mm}\) (span/depth \(\approx 10.6\), normal for a heavily loaded post-tensioned beam):
    $$A = 1.030 \times 10^{6}\ \text{mm}^2, \quad y_b = 1010.7\ \text{mm}, \quad I_g = 2.608 \times 10^{11}\ \text{mm}^4$$
    $$S_b = 2.581 \times 10^{8}\ \text{mm}^3, \quad S_t = 4.426 \times 10^{8}\ \text{mm}^3$$
    The kern distances that control the no-tension checks are \(k_b = S_b/A = 250.5\ \text{mm}\) and \(k_t = S_t/A = 429.7\ \text{mm}\). The self-weight is \(w = 1.030\ \text{m}^2 \times 24 = 24.72\ \text{kN/m}\).
  2. Service analysis. The beam is statically determinate, so there are no secondary prestress moments. Taking moments about \(B\) for the whole beam (including self-weight over the full 20 m),
    $$R_A = 592.99\ \text{kN}, \qquad R_B = 761.41\ \text{kN}$$
    The service moments at the sections that matter are
    $$M(6) = 3113.0, \quad M(8.5) = 3147.4, \quad M(11) = 3027.3, \quad M(B) = -291.2\ \text{kN}\cdot\text{m}$$
    with self-weight-only values \(M_{sw}(6) = 776.5\) and \(M_{sw}(8.5) = 837.4\ \text{kN}\cdot\text{m}\).
  3. The two no-tension conditions. Writing the bottom-fibre stress in service and the top-fibre stress at transfer and setting each to zero:
    $$-\frac{P_e}{A} - \frac{P_e e}{S_b} + \frac{M_s}{S_b} \le 0 \;\Rightarrow\; e \ge \frac{M_s}{P_e} - k_b$$
    $$-\frac{P_i}{A} + \frac{P_i e}{S_t} - \frac{M_{sw}}{S_t} \le 0 \;\Rightarrow\; e \le k_t + \frac{M_{sw}}{P_i}$$
    The first is a lower bound that falls as \(P_e\) rises; the second is an upper bound that also rises with \(P_i\). The minimum viable force is where the two meet.
  4. Prestress force and strand area. Equating the bounds at the critical section and using \(P_i = P_e (1200/960) = 1.25P_e\) gives \(P_e \approx 3.66\ \text{MN}\). Rounding up to a practical strand count, adopt 30 no. 15.2 mm seven-wire strands, \(A_{p1} = 140\ \text{mm}^2\):
    $$A_{ps} = 30(140) = 4200\ \text{mm}^2, \quad P_i = 4200(1200) = \boxed{5040\ \text{kN}}, \quad P_e = 4200(960) = 4032\ \text{kN}$$
    Detail these as five tendons of six strands in 85 mm ducts, stressed from both ends.
  5. Cable zone and adopted profile. Evaluating both bounds section by section with these forces:
    $$x = 6\ \text{m}: \; 521.5 \le e \le 583.7 \qquad x = 8.5\ \text{m}: \; 530.1 \le e \le 595.8$$
    $$x = 11\ \text{m}: \; 500.3 \le e \le 577.3 \qquad x = B: \; -322.8 \le e \le 407.6\ \text{mm}$$
    The zone between the two point loads is only about 47 mm wide, and it is flat: between two equal point loads the moment diagram is a straight line, so a single parabola with its vertex at midspan sits too low under the loads and too high at the vertex. A harped profile is therefore adopted — straight from \(e = 0\) at \(A\) to \(e = 550\ \text{mm}\) at \(x = 6\ \text{m}\), constant to \(x = 11\ \text{m}\), straight back to \(e = 0\) at \(B\), and level through the cantilever. Every section from \(x = 0\) to \(x = 20\ \text{m}\) then lies inside its zone.
  6. Stress check at the critical section. At \(x = 6\ \text{m}\) with \(e = 550\ \text{mm}\):
    $$\text{transfer:}\quad f_{top} = -0.38\ \text{MPa}, \qquad f_{bot} = -12.63\ \text{MPa} \;\le\; 0.60f_{ci} = 21.0\ \text{MPa}$$
    $$\text{service:}\quad f_{top} = -5.94\ \text{MPa} \;\le\; 0.45f'_c = 22.5\ \text{MPa}, \qquad f_{bot} = -0.45\ \text{MPa}$$
    Every fibre is in compression at both stages, so the no-tension requirement is met with a small margin at the two fibres that control.
  7. Ultimate flexural check. The strand is unbonded-equivalent bonded post-tensioning; using A23.3 Cl. 18.6.2 with \(k_p = 2(1.04 - f_{py}/f_{pu}) = 0.4229\) and \(d_p = 1600 - (1010.7 - 550) = 1139\ \text{mm}\), equilibrium of the rectangular stress block within the flange gives \(c = 146.9\ \text{mm}\), \(a = \beta_1 c = 124.2\ \text{mm} < 200\ \text{mm}\) and \(f_{pr} = 1654.6\ \text{MPa}\), so
    $$M_r = \phi_p A_{ps} f_{pr}\left(d_p - \frac{a}{2}\right) = \boxed{6737\ \text{kN}\cdot\text{m}} \;\ge\; M_f = 1.25(776.5) + 1.5(2336.5) = 4475\ \text{kN}\cdot\text{m}$$
  8. (b) Immediate deflection of C. Applying a unit downward load at \(C\) and integrating \(\int M m\,\mathrm{d}x / EI_g\) with \(E_c = 4500\sqrt{50} = 31\,820\ \text{MPa}\) and \(I_g = 2.608\times10^{11}\ \text{mm}^4\), each load case contributes
    $$\Delta_{sw} = -1.57\ \text{mm}, \quad \Delta_{loads} = -4.34\ \text{mm}, \quad \Delta_{prestress} = +4.41\ \text{mm}$$
    (negative = upward). The loads inside span \(AB\) rotate \(B\) so that the cantilever tip rises, while the prestress camber in \(AB\) rotates it the other way and pushes \(C\) down. The net immediate movement is \(\Delta_i = -1.50\ \text{mm}\), i.e. 1.5 mm upward.
  9. Long-term deflection. All the loads are sustained, so the effective modulus method applies with a creep coefficient \(\varphi_{cc} = 2.0\), i.e. \(E_{eff} = E_c/(1 + \varphi_{cc})\). Since the prestress term already uses the after-loss force \(P_e\),
    $$\Delta_{LT} = (1 + \varphi_{cc})\,\Delta_i = 3.0(-1.50) = \boxed{-4.50\ \text{mm}\ \ (4.5\ \text{mm upward})}$$
    Against the A23.3 Table 9.3 limit for a cantilever, taken as twice the projection, \(2(3000)/480 = 12.5\ \text{mm}\), the tip movement is comfortably acceptable and — being upward — will not be visible as sag.
Post-tensioned T-sectioncentroid30 strands, e = 550 mmh = 16002000 × 200 flangeweb 450all dimensions in mm
Post-tensioned T-section with the 30-strand group at e = 550 mm between the harp points.
ResultValue
T-sectionFlange 2000 × 200 mm; web 450 mm; overall depth 1600 mm
Section properties\(A = 1.030\times10^{6}\) mm²; \(y_b = 1010.7\) mm; \(I_g = 2.608\times10^{11}\) mm⁴
Kern distances\(k_b = 250.5\) mm; \(k_t = 429.7\) mm
Strand area30 – 15.2 mm strands, \(A_{ps} = 4200\) mm² (5 tendons × 6 strands)
Prestress force\(P_i = 5040\) kN; \(P_e = 4032\) kN
Tendon profileHarped: \(e = 0\) at \(A\) → 550 mm at 6 m → 550 mm at 11 m → 0 at \(B\) → 0 at \(C\)
Extreme stresses (transfer / service)−12.63 / −5.94 MPa — no tension anywhere
Ultimate check\(M_r = 6737\) kN·m ≥ \(M_f = 4475\) kN·m
Deflection of \(C\)1.50 mm up immediate; 4.50 mm up long term (limit 12.5 mm)