NivaarExam PrepOfficial exam papers ↗

07-Str-A5 · December 2014

Question 3 of 7: Simply supported composite box-girder bridge

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. 07-Str-A5 Advanced Structural Design, National Exams December 2014. Three hours, open-book (handbooks and textbooks permitted, no notes). Seven questions of equal value; any five constitute a complete paper, and only the first five presented are marked. All solutions below answer all seven, because the set is a study resource rather than an exam script. All loads shown on the figures are unfactored.

Design data supplied on the paper (SI). Concrete \(f'_c = 30\ \text{MPa}\); structural steel \(F_y = 350\ \text{MPa}\); rebar \(f_y = 400\ \text{MPa}\). Prestressed concrete: \(f_{ci} = 35\ \text{MPa}\) at transfer, \(f'_c = 50\ \text{MPa}\), \(n = 6\), \(f_{ult} = 1750\ \text{MPa}\), \(f_{y} = 1450\ \text{MPa}\), \(f_{initial} = 1200\ \text{MPa}\), losses \(= 240\ \text{MPa}\), hence \(f_{pe} = 960\ \text{MPa}\).

Reference texts.

Check: load classification. The paper prints the loads as unfactored but does not split them between dead and live. Throughout this solution every printed load is treated as a specified live load and factored at 1.5, while member self-weight is treated as dead and factored at 1.25 (NBCC 2020 combination 2, \(1.25D + 1.5L\)). If a different split is stated on exam day, re-run the same arithmetic with the stated factors — the method is unchanged.

Check: Figure 4 geometry. Read from the drawing on page 4, the beam \(AC\) is \(4 + 8 + 4 = 16\ \text{m}\) long with the rigid joint \(C\) at its right-hand end, directly over the column; the 400 kN acts at \(C\), and the 200 kN loads act at 4 m and 12 m from \(A\). Support \(A\) is drawn with the same circle-on-hatching symbol used for the rollers in Figures 1 and 2, so it is taken as a roller (vertical reaction only); base \(E\) is fixed. The frame is therefore indeterminate to the first degree.



Question 3: Simply supported composite box-girder bridge (15 + 5 = 20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

QuantityValue
Deck width (chain \(1.4 + 1.3 + 2.5 + 1.3 + 2.5 + 1.3 + 1.4\))11.7 m
Box girdersThree, 1.3 m wide, at 3.8 m centres
Deck slab275 mm reinforced concrete, \(f'_c = 30\ \text{MPa}\)
Design span / live load18 m / 20 kPa
Structural steel\(F_y = 350\ \text{MPa}\)
ConstructionUnshored; 100 % interaction assumed

Find. (a) Plate sizes for a built-up rectangular box girder that carries the wet slab alone during construction and the full factored moment compositely; (b) the number of shear studs required for full interaction.

Figure 3 - composite deck cross-section275 mm R.C. slab℄1.41.32.51.32.51.31.411.7 mbuilt-up steel box girderspan 18 m; live load 20 kPa
Figure 3 — 11.7 m deck on three 1.3 m box girders at 3.8 m centres; the 1.4 m overhangs make the exterior girder govern.

Approach. Take the exterior girder — its tributary width of 3.95 m exceeds the interior girder's 3.8 m, so it governs. Check the bare steel section against the factored construction (wet-slab) moment, then check the composite section as a plastic couple between the concrete slab in compression and the whole steel section in tension. The horizontal shear that this couple implies, divided by the factored stud resistance, gives the connector count.

  1. Deck geometry and tributary width. The dimension chain closes on the stated overall width, \(1.4 + 1.3 + 2.5 + 1.3 + 2.5 + 1.3 + 1.4 = 11.7\ \text{m}\), confirming three boxes rather than two. Girder centrelines are at 2.05, 5.85 and 9.65 m, a uniform 3.8 m spacing symmetric about the deck centreline. The exterior girder carries from the deck edge to mid-way to its neighbour:
    $$b_{trib} = \frac{2.05 + 5.85}{2} = 3.95\ \text{m} \;>\; 3.80\ \text{m}\ \text{(interior)}$$
    The effective slab width for composite action is \(b_{eff} = \min(b_{trib},\, L/4) = \min(3950,\, 4500) = 3950\ \text{mm}\).
  2. Trial box girder. Try an outside width of 1300 mm and depth 700 mm: top plate \(1300 \times 10\), bottom plate \(1300 \times 16\), two webs \(10\ \text{mm} \times 674\). Then
    $$A_s = 47\,280\ \text{mm}^2 \;(371.1\ \text{kg/m}), \quad y_b = 295.3\ \text{mm}, \quad I = 4.349\times10^{9}\ \text{mm}^4$$
    The web slenderness \(h/w = 674/10 = 67.4 \le 1700/\sqrt{350} = 90.9\) keeps the webs Class 2.
  3. Loads on the governing girder.
    $$w_{slab} = 0.275(24)(3.95) = 26.07\ \text{kN/m}, \quad w_{girder} = 3.64\ \text{kN/m} \;\Rightarrow\; w_D = 29.71\ \text{kN/m}$$
    $$w_L = 20(3.95) = 79.0\ \text{kN/m}$$
    $$M_{Df} = \frac{1.25(29.71)(18)^2}{8} = 1504.1, \qquad M_{Lf} = \frac{1.5(79.0)(18)^2}{8} = 4799.3\ \text{kN}\cdot\text{m}$$
    $$M_f = 1504.1 + 4799.3 = \boxed{6303.4\ \text{kN}\cdot\text{m}}$$
  4. Construction stage — bare steel. Before the slab hardens the steel section alone resists the wet concrete and its own weight. Elastically, \(S_t = I/(h - y_b) = 1.075\times10^{7}\ \text{mm}^3\), so
    $$M_{r,steel} = \phi S_t F_y = 0.90(1.075\times10^{7})(350) = 3385\ \text{kN}\cdot\text{m} \;\ge\; M_{Df} = 1504\ \text{kN}\cdot\text{m}$$
    Comfortable, but the top flange of a box is a plate supported along both edges with \(b/t = 1276/10 = 128\), far outside the Class 3 limit \(670/\sqrt{F_y} = 35.8\). Because that flange is in compression only during casting (afterwards it is embedded against the slab), provide two longitudinal stiffeners on the top plate, giving sub-panels of \(1276/3 = 425\ \text{mm}\) and \(b/t = 42.5\), together with internal cross-diaphragms at 4.5 m centres to control box distortion.
  5. Composite flexural resistance. Compare the slab's compressive capacity with the steel section's tensile capacity:
    $$C_r = 0.85\phi_c f'_c b_{eff} t_s = 0.85(0.65)(30)(3950)(275) = 18\,005\ \text{kN}$$
    $$T_r = \phi A_s F_y = 0.90(47\,280)(350) = 14\,893\ \text{kN} \;<\; C_r$$
    The steel yields before the slab crushes, so the plastic neutral axis lies inside the slab. The stress-block depth is
    $$a = \frac{T_r}{0.85\phi_c f'_c b_{eff}} = \frac{14\,893\times10^{3}}{65\,471} = 227.5\ \text{mm} \;<\; 275\ \text{mm}$$
  6. Moment resistance. The couple acts between the steel centroid and the centre of the stress block:
    $$\bar{z} = (h - y_b) + t_s - \frac{a}{2} = (700 - 295.3) + 275 - 113.7 = 566.0\ \text{mm}$$
    $$M_{rc} = T_r\,\bar{z} = 14\,893(0.566) = \boxed{8430\ \text{kN}\cdot\text{m}} \;\ge\; M_f = 6303\ \text{kN}\cdot\text{m}$$
    Utilisation 0.75 — the section is governed by the construction-stage depth and web slenderness rather than by composite strength, which is normal for a shallow box.
  7. Shear. The end reaction is \(V_f = (1.25 w_D + 1.5 w_L)(L/2) = 1400.8\ \text{kN}\) shared by two webs. With \(h/w = 67.4\), unstiffened (\(k_v = 5.34\)) and \(502\sqrt{k_v/F_y} = 62.0 < 67.4 \le 621\sqrt{k_v/F_y} = 76.7\), the inelastic-buckling branch applies with \(k_a = 0\):
    $$F_s = \frac{290\sqrt{F_y k_v}}{h/w} = 186.0\ \text{MPa}, \qquad V_r = \phi(2 t_w h) F_s = 2257\ \text{kN} \;\ge\; V_f$$
  8. (b) Shear connectors. For full interaction the total horizontal shear transferred between the point of zero moment and the point of maximum moment is \(V_h = \min(C_r, T_r) = 14\,893\ \text{kN}\). Using 22 mm headed studs (\(A_{sc} = 380\ \text{mm}^2\), \(F_u = 450\ \text{MPa}\)) with \(E_c = 4500\sqrt{30} = 24\,648\ \text{MPa}\), CSA S16 Cl. 17.7.2.1 gives
    $$q_r = 0.5\phi_{sc}A_{sc}\sqrt{f'_c E_c} = 130.7\ \text{kN} \;\le\; \phi_{sc}A_{sc}F_u = 136.8\ \text{kN}$$
    $$n = \frac{V_h}{q_r} = \frac{14\,893}{130.7} = 113.9 \;\Rightarrow\; \boxed{114\ \text{studs per half span},\ 228\ \text{per girder}}$$
    Placed three to a row across the 1300 mm top flange, 38 rows per half span at \(9000/38 = 237\ \text{mm}\) centres — inside the limits \(4d = 88\ \text{mm}\) minimum and 600 mm maximum.
ResultValue
Governing girder / tributary widthExterior; 3.95 m (interior 3.80 m)
Effective slab width3950 mm
Box girder1300 wide × 700 deep; top 10 mm, bottom 16 mm, webs 2 – 10 mm
Steel area / mass47 280 mm² / 371 kg/m
Factored moment (dead + live)1504.1 + 4799.3 = 6303.4 kN·m
Bare-steel resistance (construction)3385 kN·m ≥ 1504 kN·m
Composite resistance8430 kN·m (utilisation 0.75); \(a = 227.5\) mm, PNA in slab
Shear\(V_f = 1401\) kN ≤ \(V_r = 2257\) kN
Shear studs22 mm dia; \(q_r = 130.7\) kN; 114 per half span, 228 per girder (38 rows of 3 at 237 mm)
Stability details2 longitudinal top-flange stiffeners; diaphragms at 4.5 m