NivaarExam PrepOfficial exam papers ↗

07-Str-A5 · December 2014

Question 4 of 7: Plastic design of the rigid steel frame

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. 07-Str-A5 Advanced Structural Design, National Exams December 2014. Three hours, open-book (handbooks and textbooks permitted, no notes). Seven questions of equal value; any five constitute a complete paper, and only the first five presented are marked. All solutions below answer all seven, because the set is a study resource rather than an exam script. All loads shown on the figures are unfactored.

Design data supplied on the paper (SI). Concrete \(f'_c = 30\ \text{MPa}\); structural steel \(F_y = 350\ \text{MPa}\); rebar \(f_y = 400\ \text{MPa}\). Prestressed concrete: \(f_{ci} = 35\ \text{MPa}\) at transfer, \(f'_c = 50\ \text{MPa}\), \(n = 6\), \(f_{ult} = 1750\ \text{MPa}\), \(f_{y} = 1450\ \text{MPa}\), \(f_{initial} = 1200\ \text{MPa}\), losses \(= 240\ \text{MPa}\), hence \(f_{pe} = 960\ \text{MPa}\).

Reference texts.

Check: load classification. The paper prints the loads as unfactored but does not split them between dead and live. Throughout this solution every printed load is treated as a specified live load and factored at 1.5, while member self-weight is treated as dead and factored at 1.25 (NBCC 2020 combination 2, \(1.25D + 1.5L\)). If a different split is stated on exam day, re-run the same arithmetic with the stated factors — the method is unchanged.

Check: Figure 4 geometry. Read from the drawing on page 4, the beam \(AC\) is \(4 + 8 + 4 = 16\ \text{m}\) long with the rigid joint \(C\) at its right-hand end, directly over the column; the 400 kN acts at \(C\), and the 200 kN loads act at 4 m and 12 m from \(A\). Support \(A\) is drawn with the same circle-on-hatching symbol used for the rollers in Figures 1 and 2, so it is taken as a roller (vertical reaction only); base \(E\) is fixed. The frame is therefore indeterminate to the first degree.



Question 4: Plastic design of the rigid steel frame (12 + 8 = 20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

QuantityValue
Beam \(AC\)16 m; roller at \(A\); rigid joint at \(C\)
Column \(CE\)10 m; fixed at \(E\); \(D\) at mid-height
Vertical loads (specified live)200 kN at 4 m, 200 kN at 12 m, 400 kN at \(C\)
Horizontal load at \(D\)80 kN acting toward \(A\)
Steel\(F_y = 350\ \text{MPa}\), uniform \(M_p\) throughout

Find. (a) The required plastic moment and a Class 1 section that provides it; (b) the welds and stiffening of the rigid corner at \(C\).

Figure 4 - rigid frame geometry200 kN200 kN400 kN80 kNACDE4 m8 m4 m16 m5 m5 m
Figure 4 — frame geometry and loading as read from the drawing: C at 16 m, roller at A, fixed base at E.

Approach. The frame has four reaction components and three equations of equilibrium, so it is indeterminate to the first degree and needs two hinges to become a mechanism. Enumerate the independent mechanisms, take the smallest collapse load (upper bound), and confirm it with a statically admissible moment field (lower bound) so the answer is the exact plastic collapse value. The corner is then detailed to develop the member's full plastic moment.

  1. Degree of indeterminacy and possible hinge locations. The roller at \(A\) supplies one reaction, the fixed base at \(E\) three: \(4 - 3 = 1\) redundant. Hinges can form under each 200 kN load, at joint \(C\) and at base \(E\). No hinge is possible at \(A\) (a roller carries no moment), and the column between \(C\) and \(D\) carries no shear, so its moment there is constant and \(D\) can never be more critical than \(C\).
  2. Beam mechanisms. With the hinge under the 4 m load and a second at \(C\), rotating segment \(A\)–4 m by \(\theta\) drops that load 4\(\theta\) and the 12 m load \(4\theta/3\):
    $$200(4\theta) + 200\left(\tfrac{4\theta}{3}\right) = M_p\left(\tfrac{4\theta}{3}\right) + M_p\left(\tfrac{\theta}{3}\right) \;\Rightarrow\; M_p = 640\ \text{kN}\cdot\text{m}$$
    The companion mechanism, hinges at 12 m and \(C\), gives \(M_p = 3200/7 = 457.1\ \text{kN}\cdot\text{m}\). The 400 kN at \(C\) sits directly over the column and does no work in either.
  3. Sway mechanism. Because \(A\) is a roller the beam is free to translate horizontally, so the column can sway with hinges at \(C\) and \(E\). Rotating the column by \(\theta\) moves \(D\) through \(5\theta\):
    $$80(5\theta) = 2M_p\theta \;\Rightarrow\; M_p = 200\ \text{kN}\cdot\text{m}$$
  4. Combined mechanism — the one that governs. Adding the first beam mechanism to the sway mechanism in the proportion that cancels the hinge at \(C\) (sway rotation \(\theta_2 = \theta_1/3\)) leaves hinges at \(x = 4\ \text{m}\) and at \(E\) only. Equivalently, rotate the rigid body 4 m–\(C\)–\(E\) about \(E\) through \(\varphi\): the 200 kN at 4 m falls \(12\varphi\), the 200 kN at 12 m falls \(4\varphi\), the 400 kN at \(C\) moves horizontally only, and the 80 kN moves \(5\varphi\) in its own direction. The hinge at 4 m rotates \(4\varphi\) and the base hinge \(\varphi\):
    $$200(12\varphi) + 200(4\varphi) + 80(5\varphi) = M_p(4\varphi) + M_p(\varphi)$$
    $$3600\varphi = 5M_p\varphi \;\Rightarrow\; \boxed{M_p = 720\ \text{kN}\cdot\text{m}\ \text{(for the service loads)}}$$
    This exceeds every other mechanism, so it is the critical one.
  5. Lower-bound confirmation. Writing the four critical moments in terms of the single redundant \(R_A\) and a load factor \(\lambda\),
    $$M_4 = 4R_A, \quad M_{12} = 12R_A - 1600\lambda, \quad M_C = 16R_A - 3200\lambda, \quad M_E = 16R_A - 3600\lambda$$
    Maximising \(\lambda\) subject to \(|M| \le M_p\) at all four sections gives \(R_A = M_p/4\) and \(M_p/\lambda = 720\ \text{kN}\cdot\text{m}\), identical to the kinematic result — the collapse load is exact, with \(M_C = -0.44M_p\) and \(M_{12} = 0.50M_p\) both safely inside the yield surface.
  6. Required factored plastic moment. Applying the load factor to the printed (live) loads,
    $$M_{p,req} = 1.5(720) = \boxed{1080\ \text{kN}\cdot\text{m}}, \qquad Z_{req} = \frac{1080\times10^{6}}{0.90(350)} = 3.43\times10^{6}\ \text{mm}^3$$
  7. Section selection. Plastic design demands Class 1 sections (Cl. 13.5). Adopt a welded I-section with flanges \(260 \times 22\ \text{mm}\) and web \(520 \times 10\ \text{mm}\), \(d = 564\ \text{mm}\):
    $$\frac{b}{t} = 5.68 \le \frac{145}{\sqrt{350}} = 7.75, \qquad \frac{h}{w} = 52.0 \le \frac{1100}{\sqrt{350}} = 58.8 \quad\text{(Class 1)}$$
    $$Z = 3.776\times10^{6}\ \text{mm}^3, \qquad \phi Z F_y = 1189.5\ \text{kN}\cdot\text{m} \;\ge\; 1080\ \text{kN}\cdot\text{m}$$
    The column axial force at collapse is \(C_f = 1.5(800) - M_{p,req}/4 = 930\ \text{kN}\), so \(C/C_y = 0.160\) and the reduced plastic moment is
    $$\phi M_{pc} = 0.90(1.18)Z F_y\left(1 - \frac{C}{C_y}\right) = 1179.5\ \text{kN}\cdot\text{m} \;\ge\; 1080\ \text{kN}\cdot\text{m}$$
    Adopt a uniform welded I-section, 564 mm deep, 130.6 kg/m.
  8. Bracing consequence. The paper's note that lateral support exists "at all joints and load points" is not sufficient near a plastic hinge. CSA S16 Cl. 13.7 limits the unbraced length adjacent to a hinge to \(L_{cr} = (25\,000 + 15\,000\kappa)r_y/F_y\); with \(r_y = 62.3\ \text{mm}\) and \(\kappa \approx 0\) this gives \(L_{cr} \approx 4.45\ \text{m}\), against the 4 m and 8 m intervals the note implies. Additional bracing must be specified at the quarter points of the 8 m interior beam segment and at the column mid-height, otherwise the assumed mechanism cannot form.
  9. (b) The welded corner at C. A rigid corner in a plastically designed frame must develop the members' plastic moment so the hinge forms in the member, not the joint. Splitting \(\phi Z F_y\) between the plates,
    $$M_{flanges} = \phi b_f t_f (d - t_f)F_y = 976.6\ \text{kN}\cdot\text{m}, \qquad M_{web} = \phi\frac{t_w h_w^2}{4}F_y = 212.9\ \text{kN}\cdot\text{m}$$
    their sum is exactly 1189.5 kN·m. The flange force to be transferred is
    $$T_f = \phi b_f t_f F_y = 0.90(260)(22)(350) = \boxed{1801.8\ \text{kN}}$$
    Use complete-joint-penetration groove welds on both flanges with matching E49xx electrodes — a CJP weld develops the full plate strength, so no weld sizing is needed — and a 10 mm double fillet on the web.
  10. Knee panel-zone shear. The corner panel must carry the flange couple as shear:
    $$V_{pz} = \frac{\phi Z F_y}{d - t_f} - V_{col} = \frac{1189.5\times10^{6}}{542} \times 10^{-3} - 120 = 2074.7\ \text{kN}$$
    $$V_{r,pz} = 0.90(0.55F_y)d\,w = 0.90(0.55)(350)(564)(10) = 977.1\ \text{kN} \;<\; V_{pz}$$
    The unreinforced panel carries less than half the demand, so a diagonal stiffener across the square knee (\(542 \times 542\ \text{mm}\), \(45^{\circ}\)) takes the balance:
    $$F_{diag} = \frac{2074.7 - 977.1}{\cos 45^{\circ}} = 1552.2\ \text{kN}, \qquad A_{req} = \frac{1552.2\times10^{3}}{0.90(350)} = 4928\ \text{mm}^2$$
    Provide two plates \(210 \times 12\ \text{mm}\) (5040 mm²), one each side of the web.
  11. Continuity stiffeners. Opposite each beam flange the column web must receive 1801.8 kN. Provide horizontal continuity stiffeners of
    $$A_{req} = \frac{1801.8\times10^{3}}{0.90(350)} = 5720\ \text{mm}^2 \;\Rightarrow\; \text{two plates } 145 \times 20\ \text{mm (5800 mm}^2\text{)}$$
    fillet-welded to the column web and flanges, with the ends against the beam flanges ground to bear.
Figure 4 - collapse mechanism200 kN200 kN400 kN80 kNACDE4 m8 m4 m16 m5 m5 mhingehingecombined mechanism: hinges under the 200 kN load at 4 m and at the fixed base E
Governing combined collapse mechanism: hinges under the 200 kN load at 4 m and at the fixed base E, giving Mp = 720 kN·m for the service loads.
Welded rigid corner at Cbeam ACcolumn CEdiagonalstiffenerCJP groove weldcontinuity stiffeners at both beam-flange levels
Welded rigid corner at C: CJP groove welds to both flanges, diagonal knee stiffener and continuity stiffeners.
ResultValue
Degree of indeterminacy1 (roller at \(A\), fixed at \(E\)) — 2 hinges for a mechanism
Beam mechanism (4 m, C) / (12 m, C)640 / 457 kN·m
Sway mechanism (C, E)200 kN·m
Governing combined mechanismHinges at \(x = 4\) m and at \(E\); \(M_p = 720\) kN·m (service)
Required factored \(M_p\)1080 kN·m; \(Z_{req} = 3.43\times10^{6}\) mm³
Uniform sectionWelded I: flanges 2 – 260 × 22, web 520 × 10; \(d = 564\) mm; 130.6 kg/m; Class 1
Provided \(\phi Z F_y\) / \(\phi M_{pc}\)1189.5 / 1179.5 kN·m
Bracing required near hinges\(L_{cr} \approx 4.45\) m — extra braces at beam quarter points and column mid-height
Corner weldsCJP groove welds to both flanges (E49xx); 10 mm double fillet to web
Flange force / panel-zone shear1801.8 kN / 2074.7 kN demand vs 977.1 kN bare panel
Knee stiffeningDiagonal 2 – 210 × 12 mm; continuity 2 – 145 × 20 mm