23-Chem-A5 Chemical Plant Design and Economics · December 2014
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Exams — December 2014 — 04-Chem-A5 Chemical Plant Design and Economics. Three-hour, closed-book exam; any non-communicating calculator permitted. Six equally weighted (20-mark) questions are posed and the candidate answers any five; only the first five are marked. All six are answered below for completeness. Question 1 is a conceptual process-design question answered with a flow sheet and organised prose; questions 2, 3 and 4 mix a short essay with numerical work (turnover-ratio pricing, sinking-fund depreciation, and simple/compound loan interest); question 5 combines profitability and risk discussion with a return-and-payout calculation; question 6 is a safety, optimization and environmental essay.
Reference texts: M.S. Peters, K.D. Timmerhaus & R.E. West, Plant Design and Economics for Chemical Engineers (5th ed., McGraw-Hill) — the exam's named primary text (cost estimation Ch. 6, interest and investment Ch. 7, depreciation Ch. 9, profitability and payout Ch. 10, optimum design Ch. 11, plant safety and loss prevention); R. Turton et al., Analysis, Synthesis, and Design of Chemical Processes (4th ed., Prentice Hall) — flowsheet synthesis and process development; T.M. Duncan & J.A. Reimer, Chemical Engineering Design and Analysis (Cambridge, 1998) — the source of the boiling-point data used in Question 1; supporting Canadian tax practice from the Canada Revenue Agency Capital Cost Allowance classes and the half-year rule, and environmental practice from the Canadian Environmental Protection Act (CEPA) and provincial air-quality regulation.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
As in every plant-design question, the answer has two distinct layers that must be kept apart: (a) the process flow sheet — the physical sequence of unit operations that turns the CO/H2 syngas into pure methanol — and (b) the project-development flow sheet — the ordered engineering stages that carry the venture from a conceptual idea to a fully operational plant. Both are addressed below.
The stoichiometry $\mathrm{CO+2H_2\rightarrow CH_3OH}$ fixes the feed as a 2:1 H2:CO syngas, and the boiling-point data supplied are the key to the separation, because the one split in this process is a difference-in-volatility split:
The project flow sheet is the ordered set of engineering stages, each with its own decision points, that P&T Ch. 1 calls the development of a design project. Written as a sequence:
| Development stage | Key points to be considered |
|---|---|
| 1. Conceptual idea / market survey | Methanol demand and price, plant capacity, syngas source (reformed natural gas vs. purchased CO/H2), siting near feedstock and market; go / no-go on order-of-magnitude economics. |
| 2. Laboratory & thermodynamic feasibility | Reaction equilibrium and kinetics, Cu/ZnO catalyst selection and life, single-pass conversion, physical-property and phase-behaviour data (the boiling points here). |
| 3. Process synthesis / flow-sheet development | Choose and sequence unit operations (feed compression, slurry reactor, condenser/separator, recycle, distillation); fix the block flow diagram. |
| 4. Material & energy balances | Close mass and energy balances around every unit; set stream flows, compositions, temperatures and pressures, and the recycle ratio. |
| 5. Equipment sizing & mechanical design | Size the reactor, column, compressors and exchangers; select materials of construction; apply codes (ASME BPVC for the 80-bar loop). |
| 6. Cost estimation & profitability | Capital (fixed + working) and operating cost estimates; return on investment, payout, discounted-cash-flow analysis. |
| 7. Detailed engineering (PFD → P&ID) | Piping, instrumentation and control, plot plan, utilities, electrical; issue for-construction drawings. |
| 8. Safety, loss-prevention & environmental review | HAZOP, relief-system design, CO-toxicity and flammability controls, emissions and effluent permits (Canadian CEPA / provincial approvals). |
| 9. Procurement & construction | Purchase long-lead equipment, fabricate, erect, inspect and test. |
| 10. Commissioning, start-up & operation | Pre-commissioning checks, catalyst loading and reduction, controlled start-up, performance test, then steady operation and continual optimization. |