23-Chem-A5 Chemical Plant Design and Economics · December 2014
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Exams — December 2014 — 04-Chem-A5 Chemical Plant Design and Economics. Three-hour, closed-book exam; any non-communicating calculator permitted. Six equally weighted (20-mark) questions are posed and the candidate answers any five; only the first five are marked. All six are answered below for completeness. Question 1 is a conceptual process-design question answered with a flow sheet and organised prose; questions 2, 3 and 4 mix a short essay with numerical work (turnover-ratio pricing, sinking-fund depreciation, and simple/compound loan interest); question 5 combines profitability and risk discussion with a return-and-payout calculation; question 6 is a safety, optimization and environmental essay.
Reference texts: M.S. Peters, K.D. Timmerhaus & R.E. West, Plant Design and Economics for Chemical Engineers (5th ed., McGraw-Hill) — the exam's named primary text (cost estimation Ch. 6, interest and investment Ch. 7, depreciation Ch. 9, profitability and payout Ch. 10, optimum design Ch. 11, plant safety and loss prevention); R. Turton et al., Analysis, Synthesis, and Design of Chemical Processes (4th ed., Prentice Hall) — flowsheet synthesis and process development; T.M. Duncan & J.A. Reimer, Chemical Engineering Design and Analysis (Cambridge, 1998) — the source of the boiling-point data used in Question 1; supporting Canadian tax practice from the Canada Revenue Agency Capital Cost Allowance classes and the half-year rule, and environmental practice from the Canadian Environmental Protection Act (CEPA) and provincial air-quality regulation.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Optimum economic design is a design-stage optimization. The design variables — equipment sizes, configuration, operating targets — are still free to choose, and the objective is to minimise the total annual cost (or maximise profitability) by trading capital cost against operating cost. The classic examples are optimum pipe diameter, optimum reflux ratio, optimum insulation thickness and optimum heat-exchanger area: a larger, more expensive unit (higher fixed cost) lowers the ongoing operating cost, and the optimum is the size at which the sum of the two is least. The outcome fixes the plant that gets built.
Optimum operation design applies to an existing, already-built plant whose equipment is fixed. The capital is now sunk, so only the operating variables — throughput, temperature, pressure, reflux, recycle, feed split — can be adjusted, and the objective is to maximise profit (or minimise operating cost) within the constraints of the installed equipment. In short, economic (design) optimization chooses the best plant to build by balancing capital against operating cost; operation optimization chooses the best way to run the plant you already have, with capital cost no longer a variable.
The three hazards are attacked on the same logic — first try to remove or reduce the hazard at source (inherently safer design), then add engineered safeguards, then procedural and emergency controls:
| Hazard | What I would do — and how |
|---|---|
| Fire | Remove ignition sources and fuel accumulation: hazardous-area electrical classification, hot-work permits, bonding and grounding; detect early with flame/heat detectors; suppress with fixed deluge, foam and extinguishers; limit spread by fire-rated separation, spacing and drainage. |
| Explosion | Keep mixtures out of the flammable range by inerting/purging with nitrogen and by ventilation; detect with combustible-gas monitors; protect equipment with relief venting, rupture disks, flame arrestors and deflagration suppression; minimise confinement and use blast-resistant layout and spacing. |
| Toxic release | Minimise inventory of toxic material (inherently safer design), provide primary and secondary containment, route relief to scrubbers or flares; detect with toxic-gas monitors; isolate automatically with emergency shut-off valves; protect people with PPE, gas alarms and shelter/evacuation plans. |
Across all three, a formal HAZOP study, a properly designed pressure-relief and flare system, and layers of protection (the "onion" of prevention, control and mitigation) are the framework in which the specific measures sit.
Plant boilers pollute chiefly through their flue gas, their water streams, and their solid residues, so the actions target each: