23-Chem-A5 Chemical Plant Design and Economics · May 2017
Question 2 of 6: Discounted-Cash-Flow Rate of Return on Two Projects
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Closed-book exam, 3 hours; one aid sheet permitted. Six questions of equal value (20 marks each); five constitute a complete paper — full solutions to all six are given here. Questions 1 and 2 are quantitative (plant material balance and discounted-cash-flow return); Questions 3–6 are design-practice list/essay questions.
Reference texts: M.S. Peters, K.D. Timmerhaus & R.E. West, Plant Design and Economics for Chemical Engineers (5th ed., McGraw-Hill) — the exam's named primary text (process design development Ch. 2, general design considerations: plant location, safety, materials Ch. 3, interest and profitability Ch. 7–10, materials-transfer/pumps Ch. 14); R.H. Perry & D.W. Green, Perry's Chemical Engineers' Handbook (9th ed.) — pump types and selection (Sec. 10), pyrolysis kinetics data; O. Levenspiel, Chemical Reaction Engineering (3rd ed.) — first-order plug-flow space-time behind the reactor sizing in Question 1; supporting Canadian practice from CCOHS and the CSA Z767 / provincial OH&S process-safety-management framework for Question 5.
Question 2: Discounted-Cash-Flow Rate of Return on Two Projects (20 marks)
Given. Two mutually exclusive projects, each −$10 M at year 0, five annual cash inflows as tabulated (both total $20 M undiscounted: A back-loaded, B front-loaded), five-year life.
Find. The discounted-cash-flow rate of return (the interest rate that makes net present value zero — the IRR) of each project, and hence which to choose when capital is restricted.
Approach
The DCF rate of return is the discount rate $i$ at which $\text{NPV}(i)=\sum_{t=0}^{5} \dfrac{C_t}{(1+i)^t}=0$. Evaluate NPV at trial rates that bracket zero for each project and interpolate linearly; the higher IRR is preferred because capital is limited.
Figure 2.1 — Project A cash-flow diagram: −$10 M at year 0 followed by rising ("back-loaded") inflows 1.6→6.4 $106. Deferred returns give the lower IRR (≈ 22 %).
Figure 2.2 — Project B cash-flow diagram: same −$10 M outlay but falling ("front-loaded") inflows 6.5→1.6 $106. Early recovery of capital gives the higher IRR (≈ 38 %).
Set up the IRR condition. With cash flows $C_t$ ($106), find $i$ such that
$$\text{NPV}(i) = -10 + \sum_{t=1}^{5}\frac{C_t}{(1+i)^t} = 0$$
Both projects return $20 M undiscounted on a $10 M outlay, so both are profitable; the timing of the recovery sets the rate.
Bracket Project A. Discounting A's inflows:
$$\text{NPV}_A(20\%) = +0.672,\qquad \text{NPV}_A(25\%) = -0.653 \;\;(\$10^6)$$
Linear interpolation between the sign change:
$$i_A \approx 20 + 5\times\frac{0.672}{0.672+0.653} = 22.5\%$$
A straight-line interpolation across a 5-point bracket overshoots slightly, because the NPV curve is convex; refining the root until NPV = 0 gives 22.41 %.
$\boxed{\text{Project A DCF rate of return} \approx 22.4\%}$
Bracket Project B. The front-loaded inflows discount much more slowly to zero:
$$\text{NPV}_B(35\%) = +0.494,\qquad \text{NPV}_B(40\%) = -0.220 \;\;(\$10^6)$$
$$i_B \approx 35 + 5\times\frac{0.494}{0.494+0.220} = 38.5\%$$
Refining that root in the same way gives 38.39 %.
$\boxed{\text{Project B DCF rate of return} \approx 38.4\%}$
Decide. Because the two are mutually exclusive and capital is restricted, the project with the higher rate of return on the same $10 M is preferred:
$$i_B = 38.4\% \;>\; i_A = 22.4\%$$
$\boxed{\text{Choose Project B}}$ Both recover the same total money, but B returns capital earlier, so each dollar earns a higher effective rate — the decisive factor when funds are scarce and could be redeployed.
Quantity
Project A
Project B
Total undiscounted return
$20.0 M
$20.1 M
Cash-flow timing
back-loaded
front-loaded
DCF rate of return (IRR)
22.4 %
38.4 % (preferred)
Check: the roots were confirmed by bisection to NPV = 0 (22.41 % and 38.39 %). If instead the projects had unequal capital, IRR alone can mislead (it ignores project scale) and an incremental-IRR or NPV-at-the-cost-of-capital comparison would be required; here the capital is identical, so ranking by IRR is valid.