23-Chem-A5 Chemical Plant Design and Economics · May 2017
Question 3 of 6: Scope of Information for a Chemical Process Design
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Closed-book exam, 3 hours; one aid sheet permitted. Six questions of equal value (20 marks each); five constitute a complete paper — full solutions to all six are given here. Questions 1 and 2 are quantitative (plant material balance and discounted-cash-flow return); Questions 3–6 are design-practice list/essay questions.
Reference texts: M.S. Peters, K.D. Timmerhaus & R.E. West, Plant Design and Economics for Chemical Engineers (5th ed., McGraw-Hill) — the exam's named primary text (process design development Ch. 2, general design considerations: plant location, safety, materials Ch. 3, interest and profitability Ch. 7–10, materials-transfer/pumps Ch. 14); R.H. Perry & D.W. Green, Perry's Chemical Engineers' Handbook (9th ed.) — pump types and selection (Sec. 10), pyrolysis kinetics data; O. Levenspiel, Chemical Reaction Engineering (3rd ed.) — first-order plug-flow space-time behind the reactor sizing in Question 1; supporting Canadian practice from CCOHS and the CSA Z767 / provincial OH&S process-safety-management framework for Question 5.
Question 3: Scope of Information for a Chemical Process Design (20 marks)
Given / Find. A qualitative design-management question. The answer is the "design-basis" or project-scope information set agreed before detailed design begins, conventionally split into basic design data (what the plant must do) and specific design data (the fixed local/technical conditions it must do it under). At least 20 items are listed below, grouped for clarity.
A. Basic design data (product, capacity, and process definition)
Product(s) and specifications — chemical identity, purity, grades, form (solid/liquid/gas).
Production capacity / rate — design throughput (e.g. tonnes/yr) and turndown range.
Raw materials — identity, specification, and required purity of each feed.
Process chemistry / route — reactions, yields, selectivity, catalyst, by-products.
Overall material and energy balances — the process flow sheet basis.
Physical-property data — for all streams (density, viscosity, VLE, Cp, latent heats).
Operating conditions — temperatures, pressures, and residence times of each unit.
Process yield and conversion targets — per-pass and overall.
Recycle and purge philosophy — streams recovered vs. rejected.
By-product and waste streams — quantities, disposition, saleability.
B. Specific design data (site, utilities, and constraints)
Plant location / site — geography, climate, seismic and soil data.
Applicable codes and standards — ASME, CSA, API, local building and electrical codes.
Economic basis — capital budget, expected rate of return, feed/product/utility prices, project life.
Project schedule and completion date — start-up target and milestone dates.
Degree of instrumentation / control and automation philosophy.
Future-expansion and flexibility provisions — space, spare capacity, alternate feeds.
Operating labour, maintenance, and manning philosophy.
Twenty-five items are given above (more than the twenty required). In practice these are captured in a formal design basis or basis-of-design document signed off by all participating functions before detailed engineering proceeds, so that engineering, research, operations, safety, environmental, and management are working to one agreed target.