16-Civ-B2 Advanced Structural Design · December 2018
Question 6 of 7: Composite steel-concrete pedestrian bridge
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Examinations, December 2018 — 16-Civ-B2
Advanced Structural Design. Three hours, closed book (design handbooks and
textbooks permitted, no notes). Seven design questions; any five constitute a complete
paper and all questions carry equal value. Page 1 supplies the design data reproduced
below and states that all loads shown are unfactored. All seven
questions are worked here, because the paper is being used as a study
resource rather than sat under examination conditions.
Material
Property
Value
Concrete
$f'_c$
30 MPa
Structural steel
$F_y$
350 MPa
Reinforcing steel
$f_y$
400 MPa
Prestressed concrete
$f_{ci}$ at transfer
35 MPa
$f'_c$
50 MPa
modular ratio $n$
6
$f_{ult}$
1750 MPa
$f_y$ (strand)
1450 MPa
$f_{initial}$
1200 MPa
loss of prestress
240 MPa
Reference texts. The answers are written to the Canadian
limit-states codes that Engineers Canada lists for this examination:
CSA S16:19, Design of Steel Structures, with the CISC
Handbook of Steel Construction.
CSA A23.3:19, Design of Concrete Structures, with the Cement Association
of Canada Concrete Design Handbook, 4th ed.
CSA S6:19, Canadian Highway Bridge Design Code, for the pedestrian
bridge of Question 6.
National Building Code of Canada 2020, Part 4, for load combinations.
Kulak and Grondin, Limit States Design in Structural Steel;
MacGregor and Bartlett, Reinforced Concrete: Mechanics and Design
(Canadian edition); Collins and Mitchell, Prestressed Concrete Structures;
Hibbeler, Structural Analysis.
Check — load factors. Page 1 states only that the loads
shown are unfactored; it gives no dead/live split. A single factor of
$\alpha = 1.5$ is therefore applied to every printed load, and $1.25$ to self weight
that the solution itself introduces (the concrete members, the steel frame and the
plate girder). This is the NBCC 2020 Case 2 combination $1.25D + 1.5L$ read at its
live-load end. The collapse mechanisms, section classifications and interaction
equations below are independent of that choice — only the magnitudes move with
it. Serviceability answers (Question 3's deflection, Question 5's no-tension
condition, Question 6's deflection) use unfactored loads throughout, as they must.
Given. Simply supported span 16 m, deck 12 m wide, slab 240 mm
deep on five beams at 3 m centres (four spaces make up the 12 m). Unshored
construction; the beams are adequately braced. $f'_c = 30$ MPa,
$F_y = 350$ MPa.
Find. (a) the composite cross-section; (b) the number of shear
connectors.
Approach. Take an interior beam with a 3 m tributary width,
design the bare steel section for the wet-concrete stage, check the composite section
for strength and live-load deflection, then size the stud connection from the
horizontal shear that has to cross the interface.
Establish the loads on one interior beam. The slab weighs
$0.240 \times 24 = 5.76$ kPa, i.e. 17.28 kN/m over a 3 m tributary width. Add
1.49 kN/m of steel beam, 3.00 kN/m of superimposed dead load for
railings and wearing surface, and the pedestrian live load of 5.0 kPa
(CSA S6:19 Cl 3.8.9), i.e. 15.00 kN/m.
Deck cross-section. The interior beams each take a 3 m tributary width; the edge beams take half of that.
Design for the construction stage. Unshored construction means
the bare steel beam carries the wet concrete alone. With a construction live load of
0.5 kPa, $w_f = 1.25(17.28 + 1.49) + 1.5 \times 1.5 = 25.71$
kN/m and
$$M_f = \frac{w_f L^2}{8} = 823 \text{ kN}\cdot\text{m}$$
Trial W690x152: $Z_x = 4940 \times 10^3$ mm$^3$ so
$\phi M_p = 1556$ kN·m, a utilisation of 0.529. The beam is
adequately braced, so lateral torsional buckling does not reduce this.
Check the wet-concrete deflection, which actually chooses the beam.
Under the unfactored slab and steel weight the bare beam deflects
$$\Delta = \frac{5 w L^4}{384 E I_x} = 53.9 \text{ mm} = L/297$$
That is the real reason for the section size: on strength alone a much lighter beam
would do, but it would settle into the wet slab and change the deck thickness.
Specify a camber of 55 mm so that the deck finishes level.
Find the effective slab width. Cl 17.4.1 limits the effective
width to the smaller of the beam spacing and a quarter of the span:
$b_e = \min(3000,\ 16000/4) = 3000$ mm.
Check the composite section for strength. The slab in
compression can deliver $C_c = 0.85 f'_c b_e t = 18360$ kN whereas the steel in
tension can deliver only $T = A F_y = 6713$ kN, so the plastic neutral axis lies
inside the slab and the depth of the stress block is
$a = T/(0.85 f'_c b_e) = 87.7$ mm. The couple acts over
$d/2 + t - a/2 = 540.1 \text{ mm}$, giving
$$\boxed{M_r = \phi T \left(\frac{d}{2} + t - \frac{a}{2}\right)
= 3263 \text{ kN}\cdot\text{m}}$$
against the composite-stage demand
$w_f = 49.71$ kN/m, $M_f = 1591$ kN·m — a utilisation of
0.488. The end shear 398 kN is trivial against
$V_r = 1874$ kN.
Plastic composite section. Because the neutral axis lies in the slab, the whole steel section is at yield in tension.
Check the live-load deflection. Transforming the slab by
$n = E_s/E_c = 8.11$ gives a composite second moment of $5.3074 \times 10^{9}$ mm$^4$,
nearly 3.6 times the bare beam. Under the pedestrian load alone
$$\Delta_{LL} = \frac{5 w_{LL} L^4}{384 E I_{tr}} = 12.1 \text{ mm}
= L/1327$$
comfortably inside the $L/800$ that CSA S6 applies to a bridge carrying
pedestrians.
Part (b) — size one stud. Take 19 mm diameter headed studs,
100 mm long, $A_{sc} = 283.5$ mm$^2$, $F_u = 450$ MPa. Cl 17.7.2 gives
$$q_r = \min\!\left(0.5 \phi_{sc} A_{sc} \sqrt{f'_c E_c},\ \phi_{sc} A_{sc} F_u\right)
= 97.5 \text{ kN per stud}$$
Count the studs. With full shear connection the horizontal force
crossing the interface between the point of zero moment and the point of maximum
moment is the smaller of $C_c$ and $T$, i.e. $V_h = 6713$ kN. Hence
$$n = \frac{V_h}{q_r} = 69 \text{ studs per half span}
\;\Rightarrow\; \boxed{138 \text{ studs per beam}}$$
Arranged in pairs that is 35 transverse rows over each 8 m half, a pitch of
229 mm, which sits between the Cl 17.7.3 minimum of $4d = 76$ mm and the
maximum of $8t = 1920$ mm. Space them uniformly: the plastic method assumes the
connectors redistribute, so uniform spacing is both permitted and simpler to
build.
Check — pedestrian load and tributary width. The paper
gives no live load, so 5.0 kPa is adopted from CSA S6:19 Cl 3.8.9 for a pedestrian
bridge; the NBCC assembly value of 4.8 kPa would give essentially the same answer.
"Assumed uniform load distribution" is read as each interior beam taking its full 3 m
tributary width, which is the conservative reading; sharing the total deck load
equally between five beams would give 2.4 m each and reduce every action by 20 %.
Item
Design value
Steel section
W690x152, cambered 55 mm
Effective slab width
$b_e = 3000$ mm
Construction stage
$M_f = 823$ kN·m against $\phi M_p = 1556$ kN·m
Composite strength
$M_r = 3263$ kN·m against $M_f = 1591$ kN·m
Live deflection
12.1 mm $= L/1327$
Stud resistance
$q_r = 97.5$ kN (19 mm diameter)
Connectors
138 studs per beam, in 35 pairs per half span at 229 mm