Question 5 of 7: Bolted Three-Phase Fault on a Two-Machine Network
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Exams, May 2013 —
07-Elec-B7 Power Systems Engineering. Open-book, three hours, non-communicating
calculator permitted. Seven problems of equal value (20 points each); any five
constitute a complete paper and only the first five appearing in the answer book
are marked. All seven are solved here, because the set is a study
resource.
Reference texts.
M. E. El-Hawary, Electrical Power Systems: Design and Analysis,
rev. ed., IEEE Press/Wiley — the source of this paper's notation
(ABCD two-port, the “cantilever” transformer equivalent, and the
equal-area treatment of transient stability).
J. D. Glover, T. J. Overbye and M. S. Sarma, Power System Analysis and
Design, 6th ed., Cengage — transmission-line parameters (Ch. 4–5),
power flow (Ch. 6), symmetrical faults (Ch. 7), symmetrical components and
unsymmetrical faults (Ch. 8–9), transient stability (Ch. 11).
J. J. Grainger and W. D. Stevenson, Power System Analysis,
McGraw-Hill — sequence networks and fault calculations.
S. J. Chapman, Electric Machinery Fundamentals, 5th ed.,
McGraw-Hill — transformers (Ch. 2) and synchronous machines (Ch. 4–5).
Canadian practice: CSA C22.3 No. 1 Overhead Systems (conductor
temperature, sag and clearance), CAN/CSA-C88 and CSA C50 (power transformers and
insulating oil), and CSA C22.3 No. 1 Annex on fault-current duty.
Problem 5: Bolted Three-Phase Fault on a Two-Machine Network (20 points)
Find. The total current into a bolted three-phase fault at
bus 3, the share of that current contributed by each machine, and the retained
voltages at buses 1 and 2 while the fault is on.
Approach. A bolted symmetrical fault is a positive-sequence-only
problem. Combine each machine with its transformer, build the positive-sequence
reactance network, reduce it to a Thévenin equivalent at bus 3, then use
superposition (pre-fault voltages plus the fault-current injection) to get the
bus voltages and the branch flows.
Figure 5.1 — positive-sequence reactance diagram. Because both sources are 1.0∠0° pu the pre-fault network carries no current, so the pre-fault voltage everywhere — and in particular at bus 3 — is 1.0 pu.
Assemble the reactance network and note the pre-fault state.
Each generator is represented by its e.m.f. behind the series combination of its
own reactance and its step-up transformer, giving
$x_{g1} = 0.20+0.04 = 0.24$ pu and $x_{g2} = 0.25+0.06 = 0.31$ pu. Because both
e.m.f.s are stated as $1.0\angle 0^\circ$ pu and there is no load, no current
circulates before the fault and the pre-fault voltage at every bus is
$V^{(0)} = 1.0\angle 0^\circ$ pu. That is the Thévenin source voltage seen
at bus 3.
Thévenin reactance at bus 3 by network reduction. Kill
both sources (short the e.m.f.s to the reference) and look into bus 3. The two
0.1 pu legs run to bus 1 and bus 2; behind them sits a delta-free ladder in which
bus 1 reaches reference through 0.24 pu, bus 2 through 0.31 pu, and the two buses
are tied by 0.1 pu. Forming the bus admittance matrix
$\mathbf{Y}_{bus}$ for buses 1, 2 and 3 (including the source shunts) and
inverting it gives the impedance matrix, whose diagonal entry at bus 3 is the
driving-point impedance:
$$Z_{33}=j0.185514\ \text{pu}
\;\Longrightarrow\;X_{th}=0.1855\ \text{pu}$$
The same number follows by hand: the parallel combination of
$\left(0.24+0.1\right)$ pu through bus 1 and $\left(0.31+0.1\right)$ pu through
bus 2 would give $0.1859$ pu, and the 0.1 pu tie between buses 1 and 2 shaves it
to 0.1855 pu.
Part (a) — total fault current. For a bolted fault the
fault impedance is zero, so
$$I_f=\frac{V^{(0)}_3}{Z_{33}}=\frac{1.0\angle 0^\circ}
{j0.185514}
\;\Longrightarrow\;\boxed{I_f=5.3904\angle-90.00^\circ\ \text{pu}}$$
i.e. 5.3904 pu in magnitude, lagging the pre-fault voltage
by 90° because the network is purely reactive. On a 100 MVA, 230 kV base that
would be $5.390\times 100/(\sqrt{3}\times 230)
= 1353$ A, which is the number
a breaker would actually have to interrupt.
Bus voltages during the fault, by superposition. The faulted
network is the pre-fault network plus an injection of $-I_f$ at bus 3, so
$$V_i^{\,\text{fault}}=V_i^{(0)}-Z_{i3}\,I_f .$$
With $Z_{13} = j0.133622$ and
$Z_{23} = j0.137405$ pu,
$$\boxed{V_1=0.2797\angle 0^\circ\ \text{pu},\qquad
V_2=0.2593\angle 0^\circ\ \text{pu}}$$
and of course $V_3 = 0$, which is what “bolted” means. Bus 1 holds
slightly more voltage than bus 2 because it is fed through the stronger source
(0.24 pu against 0.31 pu).
Part (b) — contribution of each machine. The current out
of each machine is the drop across its own reactance divided by that reactance:
$$I_{G1}=\frac{E_1-V_1}{jx_{g1}}
=\frac{1.0-0.2797}{j0.24}
=3.0012\angle-90.00^\circ\ \text{pu}$$
$$I_{G2}=\frac{E_2-V_2}{jx_{g2}}
=\frac{1.0-0.2593}{j0.31}
=2.3893\angle-90.00^\circ\ \text{pu}$$
$$\boxed{|I_{G1}|=3.0012\ \text{pu},\qquad
|I_{G2}|=2.3893\ \text{pu}}$$
Their sum is 5.3904 pu, which reproduces $I_f$
exactly — the required check, since with no load every ampere leaving a
machine must arrive at the fault.
Where the current actually flows. It is worth separating the
machine contributions from the line flows, because they are not the same thing.
The currents arriving at bus 3 along the two faulted-bus legs are
$$I_{13}=\frac{V_1-V_3}{j0.1}=2.7972\ \text{pu},\qquad
I_{23}=\frac{V_2-V_3}{j0.1}=2.5932\ \text{pu},$$
summing again to 5.3904 pu. The difference between
$I_{G1}$ and $I_{13}$ is the
0.2040 pu that machine 1 pushes across the bus-1 to bus-2
tie line and which then reaches the fault through the bus-2 leg. A protection
engineer needs exactly this split to set the directional and differential elements
on each of the three lines.