18-Env-A3 Geotechnical and Hydrogeological Engineering · December 2018
Question 2 of 6: Earthwork Hauling and Dam Weight
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
National Exams — December 2018 — 18-Env-A3 / Geotechnical & Hydrogeological Engineering. 3 hours duration; open book exam, any non-communicating calculator permitted. FIVE (5) questions constitute a complete exam paper (the first five as they appear in the answer book are marked, 20 marks each, 100 marks total); all six printed questions are solved below for completeness.
Reference texts. Braja M. Das, Principles of Geotechnical Engineering (9th ed.) — compaction, permeability and seepage, weight–volume relations; Craig & Knappett, Craig's Soil Mechanics (8th ed.) — flow nets and composite seepage barriers; Freeze & Cherry, Groundwater (1979) — Darcy's law, the Dupuit–Thiem equation and seepage velocity.
Question 2: Earthwork Hauling and Dam Weight (20 marks)
Find. (a) the number of truck loads required to haul the cut, and the fleet size that clears the schedule; (b) the total weight of the completed dam.
Approach. (a) Bulk the bank cut volume for hauling, divide by truck capacity for total loads, then use the cycle time and shift schedule to size the fleet. (b) Apply the relative compaction to get field dry unit weight, add the optimum moisture to get field wet unit weight, and multiply by the compacted fill volume.
Part (a) — loose (bulked) volume. The 12,500 m³ bank cut swells by the bulking factor once excavated and loaded: $$V_{loose}=V_{cut}(1+0.35)=12{,}500\times1.35=16{,}875\ \text{m}^3.$$
Total truck loads. $$N_{loads}=\frac{V_{loose}}{30}=\frac{16{,}875}{30}=562.5\ \Rightarrow\ \boxed{563\ \text{loads}}\ \text{(rounded up).}$$
Cycle time per truck. Travel time $=80/40=2.0$ h; plus 15 min at each end (load + dump) $=0.5$ h fixed: $$t_{cycle}=2.0+0.5=2.5\ \text{h}.$$
Loads per truck over the job. Each truck works $2\times8=16$ h/day, so $16/2.5=6.4$ loads/truck/day, and over 7 days: $$6.4\times7=44.8\ \text{loads/truck}.$$
Fleet size. Substituting, prose connects the required total to what one truck can deliver: $$N_{trucks}=\frac{563}{44.8}=12.57\ \Rightarrow\ \boxed{13\ \text{trucks}}\ \text{needed to complete the haul in 7 days.}$$
Part (b) — field unit weight of the fill. The dam is compacted to 95% of the modified-Proctor maximum, at the optimum moisture: $$\gamma_{d,field}=RC\times\gamma_{d,max}=0.95\times21=19.95\ \text{kN/m}^3,$$ $$\gamma_{wet,field}=\gamma_{d,field}(1+w_{opt})=19.95\times1.08=21.55\ \text{kN/m}^3.$$
Total weight of the dam. Multiplying by the compacted fill volume of the dam: $$W=\gamma_{wet,field}\times V_{fill}=21.55\times8{,}500=\boxed{183{,}140\ \text{kN}}\ (\approx183.1\ \text{MN},\ \approx18{,}670\ \text{tonnes}).$$
Check: "how many truck loads will be required" is read literally as the total number of loaded trips (563); since the question supplies full cycle-time and schedule data, the fleet size needed to physically deliver those 563 loads within the 7-day/2-shift window (13 trucks) is reported alongside it as the practically decisive number — both use every given quantity. Part (b) uses the fill volume (compacted dam volume), not the cut volume, since that is the material actually placed in the finished structure. The cut area's 2% natural moisture content is background context (it describes how much water the contractor must add to reach the fill's 8% optimum) but is not itself an input to either requested quantity — a common exam pattern of supplying one more data point than a given sub-question strictly needs.