21-Mat-B1 Hydrometallurgy and Electrometallurgy · December 2014
Question 1 of 7: Highland Valley milling circuit: flow sheet, copper recovery and grinding power
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Professional Examinations, December 2014 — 10-Met-B1, Mineral Processing. Three hours, closed book, approved Casio/Sharp calculator only. Six numbered Problems (all compulsory except Problem 5) plus a two-mark Bonus Question. Problem 5's rubric asks for any SIX of eleven sketch-and-describe topics; all eleven topics are answered below.
Note on the exam title
Nothing on the paper is a hydrometallurgy (leaching, solvent extraction, electrowinning) or electrometallurgy question; the syllabus actually examined is comminution and grinding-circuit mass balance, particle settling, flotation kinetics, and mineral-processing equipment/terminology — the physical/mechanical beneficiation stage that precedes hydro- or pyro-metallurgical extraction.
Reference texts. The answers below are keyed to the works normally recommended for this syllabus code:
B. A. Wills and J. A. Finch, Wills' Mineral Processing Technology, 8th ed. — comminution and Bond's law (Ch. 6), classification and hydrocyclones (Ch. 9), gravity concentration and jigs (Ch. 10), froth flotation and flotation kinetics (Ch. 12), dense-medium separation and thickening (Ch. 11, 17).
F. F. Aplan (ed.), SME Mineral Processing Handbook — flotation reagents (collectors, frothers, activators), plant flowsheets, comminution circuit design.
A. Taggart, Handbook of Mineral Dressing — classical terminology (probable error, ratio of concentration/enrichment, jig hutch, crusher types).
Find. (a) a flow sheet of the described circuit; (b) the copper concentrate production rate in tpd; (c) the net grinding power in kW, stating the assumptions used to apply Bond's equation.
Fig. 1 — simplified block flow sheet of the Highland Valley circuit: crushing → five parallel SAG/ball-mill/cyclone grinding lines → bulk Cu-Mo rougher/scavenger flotation → thickening → Cu/Mo separation flotation, splitting into a copper stream (thicken, filter, dry) and a molybdenum stream (regrind, cyclone, cleaner column, FeCl3 leach of residual Cu, filter, dry).
Approach. (a) is answered directly from the plant description as a block flow sheet; (b) uses the two-product (feed/concentrate/tailings) metal balance; (c) applies Bond's third theory of comminution between the crusher product (taken as the mill circuit feed size $F$) and the final cyclone-overflow grind size $P$, converted to a net power draw using the plant's daily throughput.
(a) Flow sheet. Ore is trucked from the pit to two gyratory crushers (-7 in product) and conveyed to a coarse-ore stockpile. Five parallel grinding lines each reclaim ore through a SAG mill in circuit with a 0.5 in screen (oversize recycles to the SAG mill) and two ball mills operating in closed circuit with 30 in cyclones (underflow recycles to the ball mills; overflow, 80 % passing 200 microns, is the final grind). Combined cyclone overflow feeds bulk copper-molybdenum rougher/scavenger flotation (scavenger concentrate recycled to the circuit head, tailings to the impoundment). Bulk concentrate is thickened (125 ft thickener), conditioned with NaHS to depress copper minerals, and floated in a Cu/Mo separation circuit: the copper stream reports to rougher/scavenger cells and on to the final copper concentrate (thickened to 65 % solids, filtered, dried to 7 % moisture, stored at 41.4 % Cu); the molybdenum rougher concentrate is reground, classified by 6 in cyclones, upgraded in a cleaner column (tails recirculated to the 125 ft thickener), then leached with ferric chloride to strip residual copper before final filtering and drying. See Fig. 1.
(b) Copper concentrate tonnage — two-product formula. With fresh feed $F$, concentrate $C$ and tailings $T=F-C$, a metal balance on copper gives $Ff=Cc+(F-C)t$, i.e. $$C=F\cdot\dfrac{f-t}{c-t}.$$ Substituting the given grades: $$C=130{,}000\times\dfrac{0.388-0.033}{41.4-0.033}=130{,}000\times\dfrac{0.355}{41.367}=\boxed{1{,}116\ \text{tpd copper concentrate}}\ (\approx1115.6\ \text{tpd}).$$
(c) Grinding power — Bond's equation. Bond's law needs $P$ and $F$ as 80 %-passing sizes in microns. The exam gives the crusher's top size (-7 in) rather than its own 80 % passing size, so a reasonable engineering assumption is required: treat the crusher product top size as the mill-circuit feed size $F_{80}\approx7\ \text{in}=177{,}800\ \text{microns}$ (a conservative choice — the true $F_{80}$ of the crusher product is somewhat finer than its top size, which would make the true power draw slightly higher than computed here). The final grind size is the cyclone overflow, $P_{80}=200$ microns. Substituting into Bond's equation with $W_i=15$ kWh/mt: $$W=\dfrac{10(15)}{\sqrt{200}}-\dfrac{10(15)}{\sqrt{177{,}800}}=10.607-0.356=10.25\ \text{kWh/mt}.$$ Converting the daily throughput to an hourly rate, $\dot{m}=130{,}000/24=5{,}416.7$ mt/hr, so the net grinding power is $$P_{net}=W\times\dot{m}=10.25\times5{,}416.7=\boxed{55{,}500\ \text{kW}\ (\approx55.5\ \text{MW})}.$$ (Using $F_{80}=0.8\times7\ \text{in}$ instead changes the answer by under half a percent, confirming the result is not sensitive to the exact $F_{80}$ assumption within a reasonable range.)
Check. Two assumptions are load-bearing and are stated explicitly per the question's own instruction: (1) the crusher's -7 in top size is used as the Bond feed size $F_{80}$ rather than a true 80 %-passing figure, which was not supplied; (2) all five grinding lines are assumed to share the stated 15 kWh/mt work index and 80 % passing 200 micron target uniformly, so the plant-wide power is simply the specific energy times total throughput. Molybdenum content and reagent duties do not enter either calculation (Bond's law is size-reduction-only; the copper balance explicitly neglects Mo-concentrate copper per the question).