NivaarExam PrepOfficial exam papers ↗

21-Mat-B1 Hydrometallurgy and Electrometallurgy · December 2014

Question 2 of 7: Two-stage grinding circuit material balance

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Professional Examinations, December 2014 — 10-Met-B1, Mineral Processing. Three hours, closed book, approved Casio/Sharp calculator only. Six numbered Problems (all compulsory except Problem 5) plus a two-mark Bonus Question. Problem 5's rubric asks for any SIX of eleven sketch-and-describe topics; all eleven topics are answered below.

Note on the exam title

Nothing on the paper is a hydrometallurgy (leaching, solvent extraction, electrowinning) or electrometallurgy question; the syllabus actually examined is comminution and grinding-circuit mass balance, particle settling, flotation kinetics, and mineral-processing equipment/terminology — the physical/mechanical beneficiation stage that precedes hydro- or pyro-metallurgical extraction.

Reference texts. The answers below are keyed to the works normally recommended for this syllabus code:


Problem 2 — Two-stage grinding circuit material balance (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

Stream% -200 mesh% solids by weight80% passing (microns)
Rod mill discharge (RMD)5753600
Ball mill discharge (BMD, = cyclone feed)2075529
Cyclone overflow (O)3040289
Cyclone underflow (U)1575784

Fresh ore feed 100 t/h (SG 3.0); rod mill in open circuit (no return stream to the rod mill), so RMD = fresh feed = 100 t/h solids; ball mill fed by RMD + recycled cyclone underflow $U$; ball mill discharge (BMD) is the cyclone feed.

Find. (a)(i)–(ii) solids flow in the cyclone overflow and underflow; (b) dilution water added at the sump; (c) SG of the cyclone underflow slurry; (d) two operator actions that would sharpen the product.

feed 100 t/h Rod mill (open circuit) RMD 100 t/h + Ball mill Sump dilution water 116.7 t/h Pump Cyclone classifier Overflow 100 t/h, 40% solids Underflow 200 t/h, 75% solids (recycle)
Fig. 2 — two-stage grinding circuit with the solved solids flows: 100 t/h fresh feed through the open-circuit rod mill, combining with a 200 t/h cyclone-underflow recycle ahead of the ball mill; the cyclone splits its 300 t/h feed into a 100 t/h overflow (final product) and the 200 t/h underflow recycle, with 116.7 t/h of dilution water added at the sump.

Approach. Because the rod mill is open-circuit, its discharge equals the fresh feed rate, and because the cyclone underflow never leaves the ball-mill/cyclone loop, the cyclone overflow must equal the fresh feed at steady state. The circulating load (cyclone underflow) is then found from a two-product balance on the "% -200 mesh" assay across the cyclone. Water flows follow from each stream's own percent-solids figure.

  1. (a)(i)-(ii) Solids balance and circulating load. Steady-state solids balance on the whole circuit: fresh feed = final product, so the cyclone overflow $O=100$ t/h. The cyclone feed is the ball mill discharge (BMD); using the "% -200 mesh" assay as the balance component across the cyclone split, with feed assay 20 %, overflow assay 30 %, underflow assay 15 %: $$(O+U)(20)=O(30)+U(15)\ \Rightarrow\ U(20-15)=O(30-20)\ \Rightarrow\ U=2O.$$ With $O=100$ t/h, $$U=\boxed{200\ \text{t/h (cyclone underflow)}},\qquad O=\boxed{100\ \text{t/h (cyclone overflow)}}.$$ Check: BMD solids $=O+U=300$ t/h must equal RMD $+U=100+200=300$ t/h — consistent, confirming the balance.
  2. (b) Dilution water at the sump. Water entering the sump with the ball mill discharge: BMD solids 300 t/h at 75 % solids $\Rightarrow$ total slurry $=300/0.75=400$ t/h, so water in BMD $=400-300=100$ t/h. Water leaving the sump (i.e. entering the cyclone) is found from the two product streams' own percent solids: overflow slurry $=100/0.40=250$ t/h (water $=150$ t/h); underflow slurry $=200/0.75=266.7$ t/h (water $=66.7$ t/h). Total water after the split $=150+66.7=216.7$ t/h. A water balance around the sump gives the dilution addition: $$W_{dilution}=216.7-100=\boxed{116.7\ \text{t/h}}.$$
  3. (c) SG of the cyclone underflow slurry. With solids SG $=3.0$, water SG $=1.0$, and the underflow's own 75 % solids / 25 % water by weight: $$\dfrac{1}{SG_{slurry}}=\dfrac{0.75}{3.0}+\dfrac{0.25}{1.0}=0.25+0.25=0.50\ \Rightarrow\ SG_{slurry}=\boxed{2.0}.$$
  4. (d) Producing a finer product. Two independent operator actions that shift the cyclone's cut point finer (and hence sharpen/finer the overflow product): reduce the feed (throughput) rate to the ball mill, increasing residence time and grinding each particle longer before it reports to the cyclone; and reduce the cyclone feed density (add more dilution water) or feed pressure/vortex-finder diameter, which lowers the cyclone's $d_{50}$ cut size and sends more fines to the overflow at the expense of a coarser, larger-volume underflow recycle.
QuantityResult
(i) Cyclone overflow solids$\boxed{100\ \text{t/h}}$
(ii) Cyclone underflow solids$\boxed{200\ \text{t/h}}$
Dilution water added$\boxed{116.7\ \text{t/h}}$
SG of cyclone underflow slurry$\boxed{2.0}$
Circulating load ratio, $U/O$2.0 (200 %)
Check. The rod mill discharge's own 5 % -200-mesh assay is not needed to solve (a)-(c) (the cyclone-feed assay is given directly as the ball mill discharge figure) — it serves only as an internal consistency check, since mixing 100 t/h at 5 % with the 200 t/h, 15 % recycle gives a combined ball-mill-inlet assay of 11.7 % -200 mesh, sensibly lower than the 20 % leaving the mill after grinding.