22-Mec-B3 Energy Conversion and Power Generation · December 2018
Question 4 of 8: Steam Plant Design
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. 16-Mec-B3
Energy Conversion and Power Generation, National Examinations,
December 2018. Three hours, closed book. Two sections: Section A is
calculative (Questions 1–5) and Section B is descriptive
(Questions 6–8). Candidates answer four questions from Section A and two
from Section B; six questions of 10 marks each constitute a complete paper
(60 marks). Reference data for individual questions are bound in as
attachments on pages 10–12, reference formulae and constants on
pages 13–16, and Granet & Bluestein steam tables are supplied.
All eight questions are solved below, because the set is a
study resource rather than a timed attempt.
Reference texts.
Granet, I. and Bluestein, M., Thermodynamics and Heat Power, 6th ed.
— the steam tables issued with this paper, and the vapour-cycle and
gas-cycle chapters.
Çengel, Y. A. and Boles, M. A., Thermodynamics: An Engineering
Approach, 9th ed. — Brayton cycles, isentropic component
efficiencies, combined cycles, psychrometrics.
El-Wakil, M. M., Powerplant Technology — heat recovery steam
generators and pinch behaviour, cooling towers and their evaporative loss,
station heat rate and production cost, environmental impact of power
generation.
Rayaprolu, K., Boilers for Power and Process — pulverised-fuel
firing, vertical spindle mills, primary and tempering air, mill drying
capacity.
Lamarsh, J. R. and Baratta, A. J., Introduction to Nuclear
Engineering, 4th ed. — fission, the four-factor picture of a thermal
reactor, CANDU and PWR core materials.
Capital repayment / administration and maintenance
—
10 per cent / 8 per cent of capital each year
Coal price and heating value
—
100 CAD/Mg, 24 000 kJ/kg
Train car capacity, cars per train
—
50 Mg, 60
Find. Annual energy production at both the actual and the
maximum rate; the annual coal tonnage and the resulting train movements per
day; and the three annual cost streams, each expressed both in dollars per year
and in cents per kilowatt-hour, together with their total.
Approach. Energy first, because every later quantity is a
rate multiplied by it. The heat rate is stated for the whole plant on a fuel
basis, so it converts electricity directly into coal without any further use of
the boiler efficiency; the two capital-derived costs are simple percentages of
a capital sum; and each cost per unit is an annual cost divided by the annual
actual production.
Part (a) — annual energy production. A plant at its
maximum continuous rating for every hour of the year would deliver
$$E_{max}=500\,000\ \text{kW}\times 8760\ \text{h}=4.380\times 10^{9}\
\text{kWh},$$
and the capacity factor scales that to what the plant actually sends out:
$$\boxed{E_{act}=0.80\times 4.380\times 10^{9}=3.504\times 10^{9}\ \text{kWh}} .$$
Only $E_{act}$ earns revenue, so it is the denominator of every unit cost below,
while $E_{max}$ is what the capital was bought to be able to produce.
Part (b) — annual coal requirement. The heat rate is
the fuel energy needed per unit of electricity sent out, so the annual fuel
demand and hence the coal tonnage follow directly:
$$m_{coal}=\frac{E_{act}\times HR}{CV}
=\frac{3.504\times 10^{9}\times 10\,550}{24\,000}=1.5403\times 10^{9}\ \text{kg},$$
$$\boxed{m_{coal}=1.540\times 10^{6}\ \text{Mg per year}} .$$
Note that the 90 per cent boiler efficiency is not applied here: the
heat rate is already a whole-plant, fuel-based figure, and applying the boiler
efficiency a second time would double-count the stack loss.
Part (b) — train movements. Spreading the annual
tonnage evenly over the year gives $1.5403\times 10^{6}/365=4220$ Mg per day,
and one train carries $50\times 60=3000$ Mg, so
$$\boxed{n_{trains}=\frac{4220}{3000}=1.41\ \text{trains per day}} .$$
In practice this means a unit train roughly every seventeen hours, or ten
trains a week — the number that sizes the rail loop, the tippler and the
stockyard.
Part (c) — cost of coal. At the quoted price,
$$C_{coal}=1.5403\times 10^{6}\times 100=154.0\ \text{million CAD per year},$$
and dividing by the electricity actually sent out,
$$\boxed{c_{coal}=\frac{154.03\times 10^{6}}{3.504\times 10^{9}}\times 100
=4.40\ \text{cent/kWh}} .$$
Part (d) — capital repayment. The capital sum is
$2500\times 500\,000=1.250\times 10^{9}$ CAD, of which 10 per cent is repaid
annually:
$$C_{cap}=0.10\times 1.250\times 10^{9}=125.0\ \text{million CAD per year},$$
$$\boxed{c_{cap}=\frac{125.0\times 10^{6}}{3.504\times 10^{9}}\times 100
=3.57\ \text{cent/kWh}} .$$
This is a fixed charge: it is incurred whether the plant runs or not, which is
why the capacity factor matters so much to the unit cost.
Part (e) — administration and maintenance. Eight per
cent of the same capital sum,
$$C_{adm}=0.08\times 1.250\times 10^{9}=100.0\ \text{million CAD per year},$$
$$\boxed{c_{adm}=\frac{100.0\times 10^{6}}{3.504\times 10^{9}}\times 100
=2.85\ \text{cent/kWh}} .$$
Part (f) — total production cost. Adding the three
streams,
$$\boxed{c_{total}=4.40+3.57+2.85=10.82\ \text{cent/kWh}} .$$
Fuel is 40.6 per cent of the total and the two capital-derived charges together
are 59.4 per cent, so this is a capital-dominated plant — the opposite of
a simple-cycle peaking gas turbine, and the reason coal units are run
base-load.
Figure 4.1 — Part (f): the production cost broken
into its three streams, cent/kWh. Fuel is the largest single item but the two
capital-derived charges together dominate, which is what makes the capacity
factor the most sensitive assumption in the whole estimate.
Check: what the boiler efficiency is for. The stated
10 550 kJ/kWh heat rate corresponds to a whole-plant thermal efficiency of
$3600/10\,550=34.1$ per cent. Dividing by the 90 per cent boiler efficiency
gives a turbine-hall (cycle) efficiency of 37.9 per cent, which is the figure a
candidate would need if the question went on to ask for the condenser duty or
the cooling-water flow — as the May 2014 printing of this same question
did. Here parts (a) to (f) need only the whole-plant heat rate, so the boiler
efficiency is quoted but not used.