16-Civ-B2 Advanced Structural Design · December 2016
Question 5 of 7: Reinforced-concrete rigid frame — beam BC (10 + 5 + 5 marks)
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. 98-Civ-B2 Advanced Structural Design,
December 2016, three hours, closed book (design handbooks and textbooks are permitted,
no notes). Seven design questions; any five constitute a complete paper and all
questions are of equal value (20 marks each). Because the whole paper is a study
resource, all seven questions are solved here. Page 1 states that all
loads shown on the figures are unfactored, and supplies the design data used
throughout.
Reference texts.
CSA S16:19, Design of Steel Structures — Clauses 11 (classification),
13.4 (shear), 13.5 (bending), 13.7 (bracing for plastic design), 13.8 (axial
compression and bending), 14 (plate girders), 17 (composite beams).
CISC, Handbook of Steel Construction, 12th ed. — section properties and
the beam-column selection tables.
National Building Code of Canada 2020, Part 4 — load combinations.
M. P. Collins and D. Mitchell, Prestressed Concrete Structures —
permissible-stress design and tendon-zone construction.
R. C. Hibbeler, Structural Analysis, 10th ed. — continuous-beam and
rigid-frame analysis.
Design data (page 1 of the examination paper)
Quantity
Symbol
Value
Concrete
f'c
30 MPa
Structural steel
Fy
350 MPa
Reinforcing bar
fy
400 MPa
Prestressed concrete at transfer
fci
35 MPa
Prestressed concrete
f'c
50 MPa
Modular ratio
n
6
Strand tensile strength
fult
1750 MPa
Strand yield strength
fy
1450 MPa
Initial strand stress
finitial
1200 MPa
Loss of prestress
Δfp
240 MPa
Effective strand stress
fse = 1200 − 240
960 MPa
Check — load factors. Page 1 says only that
“all loads shown are unfactored”; it gives no dead/live split, so no NBCC
combination can be formed exactly. Every solution below applies a single factor of
1.5 to the loads printed on the figures and 1.25 to
self weight that the solver itself introduces (girder, slab, frame members), and states
that assumption where it is used. The choice scales the required resistances but changes
neither the collapse mechanisms, the section classifications, nor any interaction
ratio, so the engineering conclusions are unaffected. Serviceability checks
(prestress stresses, deflections, bearing pressure) use the unfactored loads as
printed.
Given. A reinforced-concrete rigid frame with fixed
bases, a 12 m beam BC between an 8 m column at A and a 10 m column at D, loaded by
100 kN horizontally at B together with 600 kN at each joint and 500 kN at mid-span.
Question data
Quantity
Symbol
Value
Beam span, B to C
L
12 m (load at 6 m)
Column AB height
h1
8 m, base fixed
Column DC height
h2
10 m, base fixed
Horizontal load at B
H
100 kN → 150 kN factored
Vertical loads at B and C
P
600 kN → 900 kN factored
Load at mid-span
Pmid
500 kN → 750 kN factored
Materials
f'c / fy
30 / 400 MPa
Find. (a) A rectangular beam section for BC with its
flexural and shear reinforcement; (b) the long-term mid-span deflection; (c) the bar
layout along the member.
Figure 4 — reinforced-concrete rigid frame with fixed bases and unequal column heights (8 m at A, 10 m at D).
Approach. Analyse the frame by the stiffness method
using the Clause 10.14.1.2 cracked-section stiffnesses (0.35Ig for the beam,
0.70Ig for the columns), design the beam for the resulting envelope, then
recompute the service deflection on Branson's effective moment of inertia and amplify it
for creep.
Part (a) — set the trial section and member stiffnesses.
Try a beam 600 mm wide by 1400 mm deep and columns 600 × 800 mm. With
$E_c=4500\sqrt{30}=24\,648$ MPa and Clause 10.14.1.2 stiffnesses,
$$I_b=0.35\frac{0.6(1.4)^3}{12}=0.0480\ \text{m}^4,\qquad
I_c=0.70\frac{0.6(0.8)^3}{12}=0.0179\ \text{m}^4$$
The beam self weight is $0.6(1.4)(24)=20.16$ kN/m, factored to 25.2 kN/m.
Analyse the frame. Solving the three-member frame with fixed
bases at two different levels gives the beam end actions
$$M_B=-328.8,\qquad M_{\text{mid}}=+2040.3,\qquad M_C=-997.8\ \text{kN}\cdot\text{m}$$
$$V_B=470.5\ \text{kN},\qquad V_C=-581.9\ \text{kN}$$
Horizontal equilibrium confirms the analysis: the base shears of 20.6 kN at A and
170.6 kN at D sum to the applied 150 kN. Note how unequal the two ends are —
the taller, more flexible column at D attracts nearly three times the beam end
moment of the stiffer 8 m column at A, because the sway caused by the horizontal
load relieves joint B and aggravates joint C.
Design the mid-span sagging steel. With 40 mm cover, 10M
stirrups and 30M bars in two layers, $d=1304$ mm and, with $\alpha_1=0.805$,
$$A_s=\frac{M_f}{\phi_sf_y(d-a/2)}\ \Rightarrow\ A_s=4941\ \text{mm}^2$$
Provide 8–30M (5600 mm2), for which
$$a=\frac{\phi_sA_sf_y}{\alpha_1\phi_cf'_cb}=202\ \text{mm},\qquad
M_r=\phi_sA_sf_y\!\left(d-\frac{a}{2}\right)=\boxed{2290\ \text{kN}\cdot\text{m}}
\ \ge\ 2040\ \text{kN}\cdot\text{m}$$
with $c/d=0.195$, so the section is firmly tension-controlled.
Design the support hogging steel. The larger support moment,
997.8 kN·m at C, needs only $A_s=2326$ mm2, and at B the demand
falls to 750 mm2. Both are close to or below
$$A_{s,\min}=\frac{0.2\sqrt{f'_c}\,b_th}{f_y}
=\frac{0.2\sqrt{30}(600)(1400)}{400}=2300\ \text{mm}^2$$
so provide 4–30M top at both supports (2800 mm2),
giving $M_r=1193$ kN·m. At joint B the minimum-steel rule, not strength, sets
the top mat.
Design the shear reinforcement. With
$d_v=\max(0.9d,\,0.72h)=1173$ mm and the simplified method
($\beta=0.18$, $\theta=35^\circ$),
$$V_c=\phi_c\lambda\beta\sqrt{f'_c}\,b_wd_v
=0.65(0.18)\sqrt{30}(600)(1173)/10^3=451\ \text{kN}$$
so at C the stirrups carry only $V_s=581.9-451.2=131$ kN, which 10M double-leg
stirrups would satisfy at 871 mm centres. Detailing therefore governs: the maximum
spacing is $\min(0.7d_v,600)=600$ mm and $A_{v,\min}=0.06\sqrt{f'_c}b_ws/f_y$ caps
10M stirrups at 400 mm. Provide 10M closed stirrups at 400 mm, tightened to
250 mm within 1.5 m of each support. The upper limit
$0.25\phi_cf'_cb_wd_v=3432$ kN is not approached.
Part (b) — find the service moment and the effective inertia.
Re-running the frame with unfactored loads gives a mid-span service moment of
1400.8 kN·m, well above the cracking moment
$$M_{cr}=\frac{f_rI_g}{y_t}=\frac{0.6\sqrt{30}\,(137.2\times10^9)}{700}
=644\ \text{kN}\cdot\text{m}$$
With $n=8.11$ and 8–30M, the cracked neutral axis lies 394 mm below the top
and $I_{cr}=49.7\times10^9$ mm4, so Branson's relation gives
$$I_e=\left(\frac{M_{cr}}{M_a}\right)^3I_g
+\left[1-\left(\frac{M_{cr}}{M_a}\right)^3\right]I_{cr}
=\boxed{58.2\times10^9\ \text{mm}^4}$$
Compute the immediate and long-term deflections. Integrating
the curvature along BC and adding the vertical movement of joints B and C gives an
immediate mid-span deflection of
$$\Delta_i=\boxed{11.9\ \text{mm}}$$
Treating the whole load as sustained — the safe reading, since page 1 gives no
dead/live split — and taking $s=2.0$ for five years or more with
$\rho'=2800/(600\times1304)=0.0036$,
$$\lambda_\Delta=\frac{s}{1+50\rho'}=\frac{2.0}{1.179}=1.70,\qquad
\Delta_{LT}=\Delta_i(1+\lambda_\Delta)=\boxed{32.1\ \text{mm}}=\frac{L}{374}$$
That is inside the $L/240$ limit of Table 9.3 for members not supporting
deflection-sensitive construction; if the 500 kN mid-span load were transient the
long-term value would fall to about 20 mm, so 32 mm is the upper bound of the
envelope.
Part (c) — lay the reinforcement out along BC. Run the
4–30M top mat continuously from face to face — it is the minimum steel
the member must carry anyway, it covers both support moments, and it doubles as the
compression steel that halves the creep multiplier at mid-span. Carry six of the
eight bottom 30M bars into both supports for the positive-moment anchorage required
by Clause 12.11.1, and stop the remaining two 1.5 m either side of mid-span, where
the moment has fallen below the six-bar resistance plus a development length. Because
the beam is 1400 mm deep, Clause 10.6.2 also calls for skin reinforcement: provide
10M side bars at 300 mm over the lower half of each face.
Mid-span section of BC — 600 × 1400 mm, 8–30M bottom in two layers, 4–30M continuous top.
Factored bending-moment diagram for BC: 2040 kN·m sagging at mid-span against 998 kN·m hogging at the taller column.
Final results
Quantity
Result
Beam section
600 mm × 1400 mm (columns 600 × 800 mm)
Design moments
MB = −329, Mmid = +2040, MC = −998 kN·m
Design shears
VB = 470, VC = 582 kN
Bottom steel
8–30M, Mr = 2290 kN·m, c/d = 0.195
Top steel
4–30M, Mr = 1193 kN·m (minimum steel governs at B)
Stirrups
10M closed at 400 mm; 250 mm within 1.5 m of supports