Question 5 of 7: Consequences of short circuits and a bolted three-phase fault
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Exams, May 2015 — 07-Elec-B7 Power Systems
Engineering. Open-book, three hours, seven problems of equal value; any five constitute a
complete paper. Every problem is answered here, because the set is intended as a study
resource rather than an exam script.
Reference texts for this subject.
M. E. El-Hawary, Electrical Power Systems: Design and Analysis, rev. ed.,
IEEE Press / Wiley — the syllabus text for 07-Elec-B7. Chapters 4 (transmission lines),
5 (synchronous machines), 3 (transformers), 6 (load flow), 7 (fault analysis) and
8 (system stability) map one-to-one onto the seven problems below.
J. D. Glover, T. J. Overbye and M. S. Sarma, Power System Analysis and Design,
6th ed., Cengage — parallel treatment of the ABCD long-line model, symmetrical
components and the equal-area criterion.
S. J. Chapman, Electric Machinery Fundamentals, 5th ed., McGraw-Hill —
salient-pole two-reaction theory and transformer loss/frequency behaviour.
CSA C22.3 No. 1, Overhead Systems, and CAN/CSA C22.2 standards give the
Canadian equipment and clearance framework these calculations feed into.
Question 5: Consequences of short circuits and a bolted three-phase fault
A short circuit collapses the impedance between a source and the fault point, so the
immediate consequence is a current many times rated — commonly ten to fifty times, and
determined almost entirely by the machine subtransient reactances and the network between them.
Four families of consequence follow.
Thermal and mechanical damage. The $I^{2}t$ let-through melts conductors,
vaporises contacts and carbonises insulation at the fault itself, while the electromagnetic
forces between parallel conductors, which scale with the square of current, distort busbars,
deform transformer windings and can tear switchgear apart. An arcing fault in a switchroom
releases enough energy to be lethal, which is the basis of the arc-flash hazard assessment
required under provincial occupational health and safety regulation and CSA Z462.
Voltage collapse in the surrounding network. The fault holds its own bus at
or near zero volts and depresses voltage across a wide area, dropping out contactors, stalling
induction motors, tripping sensitive process loads and causing converters to commutate
incorrectly. Voltage sags propagate far beyond the faulted feeder and are the single largest
cause of industrial process interruption.
Loss of synchronism and system instability. While the fault persists the
electrical power a generator can export falls sharply — to zero in the extreme case of
Question 7 — while mechanical input is unchanged, so rotors accelerate. If clearing is
slower than the critical clearing time the machine cannot decelerate within its post-fault
characteristic and pulls out of step, which can cascade into islanding and load shedding.
Equipment stress beyond the fault point. Transformers experience through-
fault forces, generators see negative-sequence rotor heating during unbalanced faults, circuit
breakers must interrupt the asymmetrical current within their rated duty, and repeated faults
age insulation cumulatively. Ground faults also drive earth-potential rise at substations and
can induce dangerous voltages in nearby communication circuits.
These consequences set the whole design chain: short-circuit studies fix breaker interrupting
ratings and bus bracing, protection settings and coordination fix clearing times, and the
resulting clearing time is what the transient-stability study of Question 7 has to live
with.
Parts (b) and (c) — the three-phase fault at bus 4
Given. The four-bus network of Figure (2), with ideal 1.0 pu sources at
buses 1 and 2 and all reactances on a common base.
Branch reactances (per unit, common base)
Branch
Reactance
Branch
Reactance
Bus 1 – bus 3
j0.15
Bus 1 – bus 4
j0.10
Bus 3 – bus 2
j0.10
Bus 4 – bus 2
j0.15
Bus 1 – bus 2 (diagonal)
j0.20
Source voltages
1.0 pu at buses 1 and 2
Find. The current in a bolted three-phase fault at bus 4, and the voltages
at buses 1 and 2 while that fault is on the system.
Figure 5 — The network of Figure (2). Both
machines are represented as ideal 1.0 pu sources directly on their buses.
Approach. Because both sources are specified as ideal 1.0 pu voltages with
no internal reactance shown, buses 1 and 2 are held at the same potential. No current can
therefore flow in any branch that connects them to each other, and the Thevenin impedance at
bus 4 reduces to the two branches that reach it from those buses.
Recognise what the ideal sources do to the network. Buses 1 and 2 are both
clamped at $1.0\angle0^\circ$ pu. Two nodes at identical potential can carry no current between
them, so the direct branch 1–2 ($j0.20$) and the series pair 1–3–2
($j0.15 + j0.10$) are inactive for this fault. Bus 3 lies between two points of equal
potential and therefore also sits at 1.0 pu with no current in either of its branches.
Form the Thevenin reactance at the fault point. Only the branches
1–4 and 4–2 remain, and they appear in parallel between the 1.0 pu source
potential and bus 4:
$$X_{th}=\frac{(j0.10)(j0.15)}{j0.10+j0.15}=j0.060\ \text{pu}$$
Compute the fault current. A bolted three-phase fault places zero
impedance from bus 4 to reference, so
$$I_f=\frac{V_{th}}{X_{th}}=\frac{1.0\angle 0^\circ}{j0.060}$$
$$\boxed{I_f = 16.667\ \text{pu}\ \angle-90^\circ}$$
The current lags by exactly 90 degrees because the network is purely reactive; a real network
with resistance would give a slightly smaller magnitude at an angle a little less than
90 degrees, and the d.c. offset would add asymmetry in the first cycles.
Split the fault current between the two sources. Each branch carries the
full 1.0 pu driving voltage across its own reactance:
$$\begin{aligned} I_{1\to4} &= \frac{1.0}{j0.10}=10.000\angle-90^\circ\ \text{pu} \\ I_{2\to4} &= \frac{1.0}{j0.15}=6.667\angle-90^\circ\ \text{pu} \end{aligned}$$
and $10.000+6.667 = 16.667$ pu confirms the parallel reduction. This split is what a
protection engineer actually needs, because it fixes the duty on each of the two breakers at
bus 4.
Part (c), evaluate the bus voltages. An ideal voltage source holds its
terminal voltage whatever current it delivers, so
$$\boxed{V_1 = V_2 = 1.0\angle 0^\circ\ \text{pu}}$$
This is a direct consequence of how Figure (2) models the machines: no subtransient reactance
is drawn between either generator and its bus, so neither bus can be depressed by the
fault.
Complete the voltage profile and check it by nodal analysis. The fault
itself forces $V_4 = 0$, and bus 3 — carrying no current, as Step 1 established —
remains at $V_3 = 1.0\angle0^\circ$ pu. Solving the four-node admittance network directly with
$V_1 = V_2 = 1$ and $V_4 = 0$ imposed returns $V_3 = 1.000\angle0^\circ$ pu and a fault current
of $16.667\angle-90^\circ$ pu, reproducing both results from an independent route.
State the engineering caveat. Real generators have subtransient
reactances of 0.1 to 0.3 pu, and if, say, $X_d'' = 0.20$ pu were placed behind each source the
same fault would give $I_f = 6.225$ pu with $V_1 = 0.357$ pu and $V_2 = 0.398$ pu — a
63 per cent reduction in fault current and a severe area-wide voltage depression. The answer
above is therefore the correct answer to the question as drawn, and it is also a useful upper
bound on fault duty, but it should not be read as a realistic voltage profile.