NivaarExam PrepOfficial exam papers ↗

24-MMP-A5 Surface Mining Methods and Design · December 2018

Question 13 of 27

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper
Paper: Surface Mining Methods and Design (09-MMP-A5), National Exam, December 2018 — 20 pages, compulsory Question 1 (40 marks, parts 1.1–1.8) plus THREE of five optional Questions 2–6 (20 marks each) normally constitute a complete paper. As a study resource, this solution answers Question 1 in full AND all five optional Questions 2–6.

Reference texts: Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (3rd ed.) — truck-shovel match factor, dragline stripping geometry, capital cost indexes, open-pit scheduling; SME Mining Engineering Handbook (3rd ed.) — equipment costing, mine dewatering, cost-index escalation.

Question 3.2 key cut and deadheading (3 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

3.2.1 Key cut. The key cut is the FIRST, narrow trench cut down through the overburden along the advancing edge of the current cut, dug before the main width of the bench is stripped — it establishes the working floor level and provides the dragline its first void to begin casting material into, and it defines the boundary/alignment the rest of the cut will follow. Carried out by the dragline itself digging a single-bucket-width trench the full depth of overburden along the strike; its importance is that an incorrectly-aligned or incorrectly-graded key cut propagates a geometry error through the entire subsequent cut, since every later pass casts relative to it.

3.2.2 Deadheading. Deadheading is moving the dragline (walking) from one position to the next WITHOUT digging — a non-productive repositioning move, e.g. walking back to the start of a new cut, or walking around an obstacle. It is carried out using the machine’s own walking mechanism (a slow, shuffling tub-lift-and-shift cycle for a walking dragline, typically well under 1 km/h). Its importance is purely economic: deadheading time is 100% non-productive (no material moved) so mine planning tries to minimise the frequency and distance of deadheading moves by sequencing cuts to keep the machine progressing steadily along one bench rather than jumping between disconnected areas.

key cut main cut (follows key cut alignment) deadhead walk →
Fig. S3.2 — key cut establishes the working floor/alignment; deadheading relocates the machine without digging.
TermPurposeImportance
Key cutfirst narrow trench, sets floor level & alignmenterrors here propagate through the whole cut
Deadheadingnon-digging repositioning move100% non-productive time — minimise by cut sequencing