24-MMP-A5 Surface Mining Methods and Design · December 2018
Question 21 of 27
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper: Surface Mining Methods and Design (09-MMP-A5), National Exam, December 2018 — 20 pages, compulsory Question 1 (40 marks, parts 1.1–1.8) plus THREE of five optional Questions 2–6 (20 marks each) normally constitute a complete paper. As a study resource, this solution answers Question 1 in full AND all five optional Questions 2–6.
Reference texts: Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (3rd ed.) — truck-shovel match factor, dragline stripping geometry, capital cost indexes, open-pit scheduling; SME Mining Engineering Handbook (3rd ed.) — equipment costing, mine dewatering, cost-index escalation.
Given. Power-law cost model P=aXb for each machine class, with a, b and unit conventions as tabulated, and unit conversions 1 lb=0.4536 kg, 1 m³=1.308 yd³, 1 tonne=1.102 short ton.
Given data — power-law capital cost models (1997 $)
Machine
a
b
X unit
Machine size given
Rotary drill
4,000
0.67
pull-down force, lb
55,000 kg
Cable shovel
5,350,000
0.74
bucket capacity, yd³
53 m³
Mechanical-drive truck
20,000
0.90
capacity, short ton
300 tonne
Find. The 1997 capital cost of each machine.
Approach. Convert each machine’s given size into the formula’s OWN native unit first, then apply P=aXb directly.