24-MMP-A5 Surface Mining Methods and Design · December 2018

Question 15 of 27: 3.6

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper
Paper: Surface Mining Methods and Design (09-MMP-A5), National Exam, December 2018 — 20 pages, compulsory Question 1 (40 marks, parts 1.1–1.8) plus THREE of five optional Questions 2–6 (20 marks each) normally constitute a complete paper. As a study resource, this solution answers Question 1 in full AND all five optional Questions 2–6.

Reference texts: Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (3rd ed.) — truck-shovel match factor, dragline stripping geometry, capital cost indexes, open-pit scheduling; SME Mining Engineering Handbook (3rd ed.) — equipment costing, mine dewatering, cost-index escalation.

Question 3.5 – 3.6 side-cast section sketch (3 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Approach. One combined cross-section, drawn to the Given data of Question 3.4, carries every item both 3.5 and 3.6 ask for — the exam explicitly builds the two sub-questions as ONE sketch annotated in stages.

high-wall (63°) spoil pile (35° repose) coal seam (3 m) dragline reach / operating radius cut depth (overburden, 25 m) stacking height pit width (40 m)
Fig. S3.5/3.6 — combined side-cast section: operating radius, stacking height, cut depth, pit width, highwall angle, spoil angle of repose and coal seam all annotated on one drawing.

The dragline sits on the far (spoil) side of the highwall, its operating radius sweeping from the coal face at the pit floor up and over to the top of the spoil pile. Cut depth is the vertical overburden thickness the machine digs through at the highwall (25 m, Given); stacking height is the vertical rise of the spoil pile above the dragline’s own working level; reach (reach factor) is the horizontal distance from the tub centerline to the farthest point the bucket can dig or dump, expressed as a fraction of the operating radius (reach factor typically 0.85–0.95 of R once boom angle/bucket geometry is allowed for). Pit width (40 m) spans from the highwall toe to the coal-face working edge; the highwall slope (63°) and spoil angle of repose (35°) are the two bounding slope lines of the section; the coal seam (3 m thick) sits at the pit floor.

ItemLocation on sketch
Operating radiusarc from tub centerline to far dig/dump limit
Stacking heightspoil pile rise above dragline floor
Cut depthvertical overburden thickness at highwall (25 m)
Reach / reach factorhorizontal component of radius to bucket limit
Pit widthhighwall toe to coal-face edge (40 m)
Highwall angle63° from horizontal
Spoil angle of repose35° from horizontal
Coal seam3 m thick, at pit floor