NivaarExam PrepOfficial exam papers ↗

07-Str-A5 · December 2015

Question 3 of 7: Composite steel–concrete warehouse floor

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Exams, December 2015 — 07-Str-A5 Advanced Structural Design. Three hours, "closed book" (textbooks and design handbooks permitted, no notes). Seven questions; any five constitute a complete paper and all are of equal value, the printed mark split being 20 marks each. All loads shown on Figures 1–4 are unfactored. All seven questions are answered here.

Design data printed on page 1 and used throughout. Concrete \(f'_c = 30\ \text{MPa}\); structural steel \(F_y = 350\ \text{MPa}\); reinforcing steel \(f_y = 400\ \text{MPa}\); prestressed concrete \(f'_{ci} = 35\ \text{MPa}\) at transfer and \(f'_c = 50\ \text{MPa}\) in service, \(n = 6\); \(f_{pu} = 1750\ \text{MPa}\), \(f_{py} = 1450\ \text{MPa}\), \(f_{p,\text{initial}} = 1200\ \text{MPa}\), losses \(= 240\ \text{MPa}\), hence \(f_{pe} = 960\ \text{MPa}\) and the loss ratio \(\eta = 0.80\).

Check: load factors and figure data. The paper states only that "all loads shown are unfactored" and gives no load classification, so every printed load is treated as a specified live load and factored at 1.5, while member and element self weight is treated as dead and factored at 1.25 (NBCC 2020 Case 2, \(1.25D + 1.5L\)). Resistance factors are \(\phi = 0.90\) (steel), \(\phi_w = 0.67\) with the additional 0.67 of CSA S16 Cl. 13.13.2.2 (welds), \(\phi_{sc} = 0.80\) (shear studs), \(\phi_c = 0.65\), \(\phi_s = 0.85\), \(\phi_p = 0.90\) (CSA A23.3). Figure 2 has a free tip at A, a roller at B and a pin at C; Figure 4 has a hatched fixed base at A and a hatched fixed end at C, with the 200 kN arrow pointing towards the frame at mid-height of the column.

Reference texts for 07-Str-A5.

Question 3: Composite steel–concrete warehouse floor (15 + 5 = 20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. From Figure 3, a 9.0 m wide floor carried on four steel beams at 2.5 m centres with 0.75 m overhangs each side (\(0.75 + 3 \times 2.5 + 0.75 = 9.0\) m), a reinforced-concrete slab on top, a design span of 14 m and a design live load of 16 kPa.

Given data (Figure 3 and its note)
QuantityValue
Floor width / beam spacing / overhang9.0 m / 2.5 m / 0.75 m
Design span14.0 m
Design live load16 kPa
Slab (adopted)150 mm, \(f'_c = 30\ \text{MPa}\), \(n = 6\)
ConstructionUnshored, 100 % interaction

Find. (a) the slab thickness, the effective flange width and the steel section for the governing interior beam; (b) the number of shear connectors.

9.0 m overall2.5 m2.5 m2.5 m0.750.75150 mm r.c. slabdesign span 14 m · live load 16 kPa · interior beam tributary width 2.5 mbₑ = 2500 mm effective slab widthflanges 250 × 20web 550 × 10 (d = 590)a = 118 mm
Figure 3 floor cross-section, and the composite design section of one interior beam with its 2500 mm effective slab width.

Approach. Design the interior beam, whose 2.5 m tributary width governs over the 2.0 m of the edge beams; check the bare steel section for the wet-concrete construction stage because the floor is unshored, then check the composite section at ultimate and the composite stiffness for live-load deflection; finally transfer the full horizontal shear with studs.

  1. Slab and loads on the interior beam. A 150 mm slab spanning 2.5 m continuously needs \(A_s \approx 455\ \text{mm}^2/\text{m}\) at \(M_f \approx w_fL^2/10 = 17.8\ \text{kN}\cdot\text{m/m}\); use 15M at 300 mm each way. For the beam, with a trial welded section of web \(550 \times 10\) and flanges \(250 \times 20\) (\(A_s = 15\,500\ \text{mm}^2\), \(d = 590\ \text{mm}\), 1.19 kN/m), $$w_D = 0.150(24)(2.5) + 1.19 = 10.19\ \text{kN/m}, \qquad w_L = 16(2.5) = 40.0\ \text{kN/m}$$ $$w_f = 1.25(10.19) + 1.5(40.0) = 72.74\ \text{kN/m} \;\Rightarrow\; M_f = \frac{w_fL^2}{8} = \boxed{1782\ \text{kN}\cdot\text{m}}, \quad V_f = 509\ \text{kN}$$
  2. Construction stage (unshored). Before the slab hardens the bare steel beam alone carries the wet concrete and its own weight, \(M_f = 1.25(10.19)(14)^2/8 = 312\ \text{kN}\cdot\text{m}\). The section is Class 1 (\(b/t = 6.0 < 7.75\), \(h/w = 55.0 < 58.8\)), so \(\phi Z F_y = 1136\ \text{kN}\cdot\text{m}\) — ample. This check is what makes unshored construction legitimate; it is not a formality, because on deeper spans it can size the beam.
  3. (a) Effective width and the composite plastic capacity. CSA S16 Cl. 17.4 gives $$b_e = \min\left(\frac{L}{4},\ \text{beam spacing}\right) = \min(3500,\ 2500) = \boxed{2500\ \text{mm}}$$ The steel can deliver \(T = \phi A_s F_y = 4882.5\ \text{kN}\), while the slab could resist \(0.85\phi_c f'_c b_e t = 6216\ \text{kN}\). Since \(T\) is the smaller, the plastic neutral axis lies inside the slab at $$a = \frac{T}{0.85\phi_c f'_c b_e} = 117.8\ \text{mm} \;<\; 150\ \text{mm}$$ and the whole steel section is in tension, so the lever arm runs from its centroid to the centroid of the slab block: $$M_{rc} = T\left(\frac{d}{2} + t - \frac{a}{2}\right) = 4882.5\left(295 + 150 - 58.9\right)\times10^{-3} = \boxed{1885\ \text{kN}\cdot\text{m}} \;>\; 1782\ \text{kN}\cdot\text{m}$$
  4. Shear and deflection. The web takes the shear alone: with \(h/w = 55.0\), \(F_s = 670\sqrt{F_y}/(h/w) = 227.9\ \text{MPa}\) and \(V_r = \phi A_w F_s = 1128\ \text{kN} > 509\ \text{kN}\). For deflection, transform the slab with the paper's \(n = 6\), giving \(b_{tr} = 416.7\ \text{mm}\), an elastic neutral axis 148.5 mm below the top (just inside the slab) and \(I_{tr} = 2.769 \times 10^{9}\ \text{mm}^4\). Then $$\Delta_{LL} = \frac{5w_LL^4}{384EI_{tr}} = 36.1\ \text{mm} \;<\; \frac{L}{360} = 38.9\ \text{mm}$$ The dead-load deflection is carried by the bare steel, \(26.8\ \text{mm}\), so camber the beams 25 mm.
  5. (b) Horizontal shear to be transferred. For full interaction the connectors between the point of maximum moment and the nearer support must carry the smaller of the two capacities computed in step 3: $$V_h = \min\left(\phi A_sF_y,\ 0.85\phi_cf'_cb_et\right) = 4882.5\ \text{kN}$$
  6. (b) Stud capacity and count. With \(E_c = 4500\sqrt{30} = 24\,648\ \text{MPa}\) and 19 mm studs (\(A_{sc} = 283.5\ \text{mm}^2\), \(F_u = 450\ \text{MPa}\)), CSA S16 Cl. 17.7.2.2 gives $$q_{rs} = 0.5\phi_{sc}A_{sc}\sqrt{f'_cE_c} = 97.5\ \text{kN} \;\le\; \phi_{sc}A_{sc}F_u = 102.2\ \text{kN}$$ so \(q_{rs} = 97.5\ \text{kN}\) and $$n = \frac{V_h}{q_{rs}} = \frac{4882.5}{97.5} = 50.1 \;\Rightarrow\; \boxed{51\ \text{studs per half span}}$$ that is 102 studs per beam. Placed in pairs, 26 rows at 260 mm satisfy the Cl. 17.7.2.4 limits (minimum \(4d = 76\) mm, maximum the lesser of 800 mm and \(4t = 600\) mm).
Question 3 — final results
ItemValue
Slab150 mm, 15M at 300 mm each way
Steel beam (interior, governs)Welded I: web 550 × 10, flanges 250 × 20 (d = 590 mm)
Effective slab width \(b_e\)2500 mm
\(M_f\) / \(M_{rc}\)1782 / 1885 kN·m  (ratio 0.95)
Construction-stage \(M_f\) / \(\phi ZF_y\)312 / 1136 kN·m
\(V_f\) / \(V_r\)509 / 1128 kN
Live-load deflection36.1 mm < L/360 = 38.9 mm; camber 25 mm
Horizontal shear \(V_h\) / stud \(q_{rs}\)4882.5 kN / 97.5 kN
Connectors51 per half span = 102 per beam; 26 pairs at 260 mm