16-Civ-B2 Advanced Structural Design · December 2017
Question 6 of 7: Limit states design of the reinforced concrete member ABC
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Exams,
December 2017, 16-Civ-B2 Advanced Structural Design — 3 hours, open book
(design handbooks and textbooks permitted). Seven design questions of equal
value; any five constitute a complete paper. All seven are solved here
because the set is a study resource. Page 1 supplies the design data used
throughout: concrete $f'_c = 30$ MPa; structural steel $F_y = 350$ MPa; rebar
$f_y = 400$ MPa; prestressed concrete $f_{ci} = 35$ MPa at transfer,
$f'_c = 50$ MPa, $n = 6$, $f_{ult} = 1750$ MPa, $f_{py} = 1450$ MPa,
$f_{initial} = 1200$ MPa, losses $= 240$ MPa. Page 1 also states that
all loads shown are unfactored.
Reference texts. CSA S16:19 Design of Steel
Structures (Cl 8.5, 13.4, 13.6, 13.8, 14.3–14.6, 17); CISC
Handbook of Steel Construction, 11th ed.; CSA A23.3:19 Design of
Concrete Structures (Cl 9.8, 10, 11, 15, 18); CSA S6:19 Canadian
Highway Bridge Design Code; Kulak & Grondin, Limit States Design
in Structural Steel, 10th ed.; MacGregor & Bartlett, Reinforced
Concrete: Mechanics and Design (Canadian ed.); Collins & Mitchell,
Prestressed Concrete Structures.
Check: load factors. The paper states only that the loads
are unfactored and gives no dead/live split. Throughout, the printed loads are
taken as one variable-load case and factored by $1.5$, while self weight that
the solver introduces (concrete frames, the prestressed girder, the bridge
deck) is factored by $1.25$, per NBCC 2020 Table 4.1.3.2. The mechanisms,
section classifications and interaction equations are unaffected by that
choice; only the magnitudes scale.
Question 6: Limit states design of the reinforced concrete member ABC (14 + 6 marks)
Given. From Figure 5: an L-frame whose horizontal
member A–B–C is built into a wall at A and spans $6 + 6 = 12$ m to
joint C, from which a 10 m column runs down to a pinned base at D. Point loads
of 400 kN act at B and 600 kN at C. Materials are $f'_c = 30$ MPa and
$f_y = 400$ MPa.
Quantity
Symbol
Value
Beam A–B–C span
$L$
12 m (B at mid-span)
Column C–D height
$h$
10 m, pinned at D
Load at B / at C (unfactored)
$P_B$ / $P_C$
400 / 600 kN
Trial beam section
$b \times h$
500 × 1200 mm
Trial column section
$b \times h$
600 × 800 mm
Concrete / steel
$f'_c$ / $f_y$
30 / 400 MPa
Beam self weight
$w$
14.4 kN/m
Find. Flexural and shear reinforcement for member
ABC, with a layout drawing.
Figure 5: the horizontal member ABC is built in at A and propped at C by the 10 m column, which is pinned at D. Factored beam moments are shown alongside.
Approach. Analyse the twice-redundant frame by the
force method using the Cl 10.14.1.2 cracked-section stiffnesses, take the
envelope of hogging and sagging moments and the peak shear, then proportion the
section with the rectangular stress block and detail the stirrups.
Factor the loads.
$$\begin{gathered}P_B = 1.5(400) = 600\ \text{kN}, \\ P_C = 1.5(600) = 900\ \text{kN}, \\ w = 1.25(14.4) = 18.0\ \text{kN/m}.\end{gathered}$$
The 900 kN at C acts directly over the column and does no work on the beam
except through the joint.
Set up the analysis. A is fully fixed (3 restraints) and
D is pinned (2), so with three equations of equilibrium the frame is twice
redundant. Cl 10.14.1.2 gives the stiffnesses to use in a frame analysis:
$0.35I_g$ for the beam and $0.70I_g$ for the column, i.e.
$$I_b = 0.35\frac{500(1200)^3}{12} = 2.52\times10^{10},\qquad
I_c = 0.70\frac{600(800)^3}{12} = 1.792\times10^{10}\ \text{mm}^4 .$$
Solve for the redundants. Releasing the horizontal and
vertical reactions at D and applying the unit-load method over both members
gives
$$\begin{gathered}V_D = 1222.9\ \text{kN}, \\ H_D = 43.6\ \text{kN}, \\ V_A = 493.1\ \text{kN}.\end{gathered}$$
Because the column base is pinned, the horizontal reaction is simply the column
shear, $H = |M_C|/h$.
Design moments and shear. The resulting beam diagram is
$$\begin{gathered}M_A = -1456\ \text{kN}\cdot\text{m}\ \text{(hogging)}, \\ M_B = +1178\ \text{kN}\cdot\text{m}\ \text{(sagging)}, \\ M_C = -436\ \text{kN}\cdot\text{m},\end{gathered}$$
with the maximum shear $V_f = 493.1$ kN at A. The value at A sits between the
propped-cantilever bound (1674 kN·m, a pin at C) and the fixed-fixed
bound (1116 kN·m, a rigid support at C), as it must — the column
supplies partial rotational restraint.
Effective depth. With 40 mm cover, 10M stirrups and 30M
bars,
$$d = 1200 - 40 - 11.3 - \tfrac{29.9}{2} = 1134\ \text{mm}.$$
Flexural steel at A. Solving
$\phi_s A_s f_y(d - a/2) = M_f$ with
$a = \phi_s A_s f_y/(\alpha_1\phi_c f'_c b)$ and $\alpha_1 = 0.805$:
$$A_s = 4099\ \text{mm}^2 \;\Rightarrow\; \boxed{\text{6 – 30M top}}
\ (4200\ \text{mm}^2).$$
Then $a = 181.9$ mm, $c/d = 0.179 \ll 0.5$, so the section is comfortably
tension-controlled, and $M_r = 1489$ kN·m against $M_f = 1456$
kN·m. Six 30M bars fit in one layer: they need
$6(29.9) + 5(42) = 389$ mm against the 400 mm clear width.
Flexural steel at B and at C. The same solve gives
$A_s = 3259$ mm$^2$ at B, so provide 5 – 30M bottom
($3500$ mm$^2$, $M_r = 1259$ kN·m). At C the demand is only
$A_s = 1155$ mm$^2$, below the minimum
$$A_{s,min} = \frac{0.2\sqrt{f'_c}}{f_y}b_t h
= \frac{0.2\sqrt{30}}{400}(500)(1200) = 1643\ \text{mm}^2,$$
so minimum steel governs: provide 3 – 30M top ($2100$ mm$^2$)
across the joint and anchor it into the column.
Shear. With
$d_v = \max(0.9d, 0.72h) = 1020$ mm and the simplified method
($\beta = 0.18$, $\theta = 35^\circ$),
$$V_c = \phi_c\lambda\beta\sqrt{f'_c}\,b_w d_v
= 0.65(0.18)\sqrt{30}(500)(1020)/10^3 = 327\ \text{kN},$$
so the stirrups must carry $V_s = 493.1 - 327 = 166$ kN. Ten-millimetre
double-leg stirrups ($A_v = 200$ mm$^2$) would satisfy strength at
$$s = \frac{\phi_s A_v f_y d_v \cot\theta}{V_s} = 597\ \text{mm}.$$
Detailing limits govern the stirrup spacing. Because
$V_f = 493$ kN is far below $0.125\phi_c f'_c b_w d_v = 1244$ kN, Cl 11.3.8.1
caps the spacing at $\min(0.7d_v, 600) = 600$ mm; but the minimum-shear-
reinforcement rule
$A_v \ge 0.06\sqrt{f'_c}\,b_w s/f_y$ caps it at 487 mm. Adopt
$$\boxed{\text{10M double-leg stirrups at 450 mm throughout}},$$
tightened to 250 mm over the first 1.5 m from A where the shear is largest.
Reinforcement layout for member ABC: 6-30M top at A, 5-30M bottom through the span, 3-30M top at C, with 10M double-leg stirrups.