Question 5 of 7: Three-Phase Faults on a Meshed Network
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Exams, May 2014 —
07-Elec-B7 Power Systems Engineering. Open-book, three hours, non-communicating
calculator permitted. Seven problems of equal value; any five constitute a
complete paper and only the first five appearing in the answer book are marked.
All seven are solved here, because the set is a study resource.
Reference texts.
M. E. El-Hawary, Electrical Power Systems: Design and Analysis,
rev. ed., IEEE Press/Wiley — the source of this paper's notation (the ABCD
two-port, the “cantilever” transformer equivalent, the two-reaction
salient-pole model, and the equal-area treatment of transient stability).
J. D. Glover, T. J. Overbye and M. S. Sarma, Power System Analysis and
Design, 6th ed., Cengage — transmission-line parameters and the
long-line model (Ch. 4–5), power flow (Ch. 6), symmetrical faults (Ch. 7),
symmetrical components and unsymmetrical faults (Ch. 8–9), transient
stability (Ch. 11).
J. J. Grainger and W. D. Stevenson, Power System Analysis,
McGraw-Hill — network reduction, sequence networks and fault calculations.
S. J. Chapman, Electric Machinery Fundamentals, 5th ed.,
McGraw-Hill — transformer equivalent circuits and tests (Ch. 2),
synchronous machines (Ch. 4–5).
Canadian practice: CSA C22.1 Canadian Electrical Code Section 10
(grounding and bonding), CSA C22.3 No. 1 Overhead Systems, and
IEEE Std 142 (Green Book) for industrial system grounding.
Check — two printing defects in the source.
Problem 7(a) prints the active load as “2.24.1 p.u.”; it is read here as
2.241 p.u. The reading is not load-bearing: taking 2.24 p.u.
instead moves the initial power angle by 0.005° and the maximum swing by
0.01°. Problem 6(b) and 6(c) each print “a single line to ground fault
… on phases B and C”, which is self-contradictory; the fault
involving two phases and ground is the double line-to-ground
fault, and that is what is solved. The single-line-to-ground value is carried
alongside so that either reading is served.
Problem 5: Three-Phase Faults on a Meshed Network (5 + 7.5 + 7.5 points)
Part (a) — Main causes of short-circuit faults on Canadian systems
Lightning is the single largest cause of faults on overhead
transmission and distribution in Canada. A stroke to a phase conductor, or a
back-flashover from a struck shield wire or tower whose footing resistance is
high, puts a steep-fronted impulse across the insulator string and causes a power
follow-through arc. Most such faults are single-line-to-ground and transient,
which is why single-pole and three-pole autoreclosing is standard practice and why
tower-footing resistance is a design parameter on Canadian Shield rock.
Weather and mechanical loading come next and are distinctively
Canadian in character. Freezing rain accretes radial ice that can exceed the
mechanical design load — the January 1998 ice storm in eastern Ontario and
Quebec collapsed towers outright. Asymmetric ice shedding causes conductors to jump
and clash; steady crosswinds on iced conductors cause galloping, which brings phases
together at mid-span; and heavy wet snow does both. Wind alone reduces phase
clearances and blows debris and tree limbs into the line. In summer, conductor sag
increases with load and ambient temperature and can close the clearance to
vegetation.
Vegetation and wildlife account for a large share of
distribution outages: tree contact under wind or growth into the right-of-way,
and birds and small mammals bridging phase-to-ground clearances at poles and
substations. Wildfire has become a leading cause in the British
Columbia and Alberta interior, because smoke and airborne ash sharply reduce the
flashover strength of the air gap even where the fire never touches the line.
Contamination matters on the coasts and near industry: salt fog on
the Lower Mainland and the Maritimes, and cement or fertiliser dust inland, form a
conducting film that flashes over when it is wetted by light rain or dew.
The remaining causes are of the system's own making. Insulation
ageing and equipment failure — moisture ingress into transformer
and cable insulation, partial-discharge erosion, bushing and surge-arrester
failures — produce permanent faults that no reclosing can clear.
Switching and temporary overvoltages, including ferroresonance
and energisation transients, can break down already weakened insulation.
Third-party damage is the dominant cause on underground systems:
dig-ins by excavators despite one-call locate requirements. And
human error — racking in a breaker on a grounded bus,
leaving safety grounds applied, incorrect switching orders — remains a real
contributor, which is why the fault currents computed below matter: equipment must
interrupt them and personnel must be protected from the arc flash they produce.
Parts (b) and (c) — Fault calculations
Given.
Element
Symbol
Reactance (pu)
Source at bus 1
$x_{g1}$
0.175
Source at bus 2 plus its transformer to bus 3
$x_{g2}+x_t$
$0.125+0.05 = 0.175$
Line 1–3, bus 1 to F1
$x_{1F}$
0.225
Line 1–3, F1 to bus 3
$x_{F3}$
0.100
Line 1–4
$x_{14}$
0.250
Line 1–5
$x_{15}$
0.175
Line 5–4
$x_{54}$
0.150
Line 3–4
$x_{34}$
0.150
Line 1–4 in Figure 3-b, bus 1 to F2 / F2 to bus 4
$x_{1F2},\ x_{F2,4}$
0.150 / 0.100
Both source internal voltages
$E$
$1.0\angle 0^{\circ}$
Find. The voltage at bus 1 during a bolted three-phase fault
at F1 on line 1–3, and then the voltage at bus 1 during a bolted three-phase
fault at F2 on line 1–4 after line 1–3 has been removed.
Figure 5a — Positive-sequence reactance diagram for fault F1. The 0.125 source and the 0.05 transformer at bus 2 have been added in series and drawn as a single 0.175 branch to bus 3.
Figure 5b — Reactance diagram for fault F2, with line 1–3 removed. Bus 3 now reaches bus 1 only through bus 4.
Approach. With both source voltages equal to
$1.0\angle 0^{\circ}$ the two machines can be merged into a single reference node, after which each
case reduces to a bridge that yields to one delta-to-star transformation. The fault
current follows from the Thévenin reactance, and back-substitution through
the reduction gives the bus voltage directly.
Part (b) — Collapse the radial and series paths first.
Bus 2 carries nothing but the source and the transformer, so those add in series:
$0.125+0.05=0.175$ from the reference to bus 3. Bus 5 lies on a simple path
from bus 1 to bus 4, so it also collapses:
$$x_{1\text{-}5\text{-}4}=0.175+0.150=0.3250$$
which is in parallel with the direct line 1–4:
$$x_{14}^{eq}=\frac{(0.3250)(0.250)}{0.3250+0.250}=0.141304$$
Adding the remaining line 3–4 gives a single equivalent branch from bus 1 to
bus 3 that bypasses the faulted line:
$$x_{1\text{-}3}^{alt}=0.141304+0.150=0.291304$$
Transform the remaining delta into a star. What is left is a
bridge: the reference node, bus 1 and bus 3 form a triangle of
$0.175$, $0.175$ and $0.291304$, with the fault node hanging between buses 1 and 3.
With $\Sigma=0.175+0.175+0.291304=0.641304$, the star arms are
$$\begin{aligned}
Z_N&=\frac{(0.175)(0.175)}{\Sigma}=0.047754\\
Z_1&=\frac{(0.175)(0.291304)}{\Sigma}=0.079492\\
Z_3&=\frac{(0.175)(0.291304)}{\Sigma}=0.079492
\end{aligned}$$
Assemble the Thévenin reactance at the fault. From the
fault point F there are now exactly two paths to the star centre O, and from O a
single arm to the reference:
$$\begin{aligned}
Z_{F\text{-}1\text{-}O}&=0.225+0.079492=0.304492\\
Z_{F\text{-}3\text{-}O}&=0.100+0.079492=0.179492
\end{aligned}$$
$$X_{th}=Z_N+\frac{(0.304492)(0.179492)}{0.304492+0.179492}=0.047754+0.112925=\boxed{j0.160679\ \text{pu}}$$
$$I_F=\frac{1.0}{j0.160679}=6.2236\angle-90^{\circ}\ \text{pu}$$
Back-substitute to the voltage at bus 1. The whole fault
current flows through $Z_N$, so the star-centre voltage is
$$V_O=1.0-I_F Z_N=1.0-(6.2236)(0.047754)=0.702797\ \text{pu}$$
That voltage then drives the two arms in parallel, and the share taken by the arm
containing bus 1 is
$$I_{F\text{-}1\text{-}O}=\frac{0.702797}{0.304492}=2.308101\ \text{pu}$$
Since bus 1 sits between that arm and the bolted fault (which is at zero volts),
the bus voltage is simply the drop across the 0.225 section:
$$\boxed{V_1=(2.308101)(0.225)=0.5193\ \text{pu}}$$
The two arm currents sum to $2.308101+3.915490=6.2236$, which reproduces 6.2236 —
a free check that the star transformation and the division were both done right.
Part (c) — Rebuild the network with line 1–3 out.
With line 1–3 removed, bus 3 can reach bus 1 only through bus 4, and bus 5
again collapses into a single path:
$$\begin{aligned}x_{N\text{-}4}&=0.175+0.150=0.3250 \\ x_{1\text{-}4}&=0.175+0.150=0.3250\end{aligned}$$
The triangle is now the reference, bus 1 and bus 4, with the fault F2 hanging
between buses 1 and 4. With $\Sigma'=0.175+0.3250+0.3250=0.8250$,
$$\begin{aligned}Z_N'&=0.068939 \\ Z_1'&=0.068939 \\ Z_4'&=0.128030\end{aligned}$$
Compute the second fault current and the bus voltage.
The two arms from the fault to the star centre are
$0.150+0.068939=0.218939$ and $0.100+0.128030=0.228030$, so
$$X_{th}'=0.068939+\frac{(0.218939)(0.228030)}{0.218939+0.228030}=\boxed{j0.180636\ \text{pu}}$$
$$\begin{aligned}I_F'&=\frac{1.0}{0.180636}=5.5360\ \text{pu} \\ V_O'&=1.0-(5.5360)(0.068939)=0.618351\ \text{pu}\end{aligned}$$
$$I'_{F\text{-}1\text{-}O}=\frac{0.618351}{0.218939}=2.824302\ \text{pu}
\;\Rightarrow\;\boxed{V_1'=(2.824302)(0.150)=0.4236\ \text{pu}}$$
Interpret and cross-check both results. The second fault is
electrically closer to bus 1 — 0.150 pu of line instead of 0.225 pu
— and the loss of line 1–3 has weakened the network, so although the
total fault current is smaller (5.5360 against 6.2236 pu, because the Thévenin
reactance rose from 0.160679 to 0.180636), the voltage at bus 1 is lower:
0.4236 against 0.5193 pu. That is the point of the question: fault-current
magnitude and depth of voltage depression are governed by different things, the
first by the Thévenin impedance at the fault and the second by the electrical
distance between the fault and the bus of interest. Both results were confirmed
independently by inverting the full five-node bus admittance matrix and forming
$V_k = 1 - Z_{kF}/Z_{FF}$; the two methods agree to twelve significant figures.